HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
7
Buildings
2
Parking
47 spaces
Land area
1,068 sq m
Sanctioned built-up
2,409 sq m

Timeline

RERA registeredFeb 2025
Proposed completionMar 2028
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Landscaping & Tree…0%
Solid Waste Manage…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
External finishes20%
Stairs & lifts60%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SHREE BUILDCON

PartnershipPromoter type
Nashik, MAHARASHTRABased in
18Projects
12Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,065 homeson the public record across 18 projects
40,173 sq mbuilt-up filed
32,833 sq mland declared
₹149.09 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Ahmedabad Municipal CorporationMunicipal / Corporation3 of 14 projects
Nashik Municipal CorporationMunicipal Corporationthis project3 of 14 projects
Ahmedabad Urban Development AuthorityUrban Development Authority2 of 14 projects
Others2 of 14 projects
Bhavnagar Municipal CorporationMunicipal / Corporation1 of 14 projects
Gandhinagar Municipal CorporationMunicipal / Corporation1 of 14 projects
Mumbai Metropolitan Region Development AuthorityMetropolitan Development Authority1 of 14 projects
Rajkot Municipal CorporationMunicipal / Corporation1 of 14 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Nashik (M Corp.)
Taluka
Nashik
District
Nashik
Pincode
422003
Survey no.
PLOT NO.54 S.N. 576/1
North boundary
PLOT NO 51 52 AND 53
East boundary
PLOT NO 55
South boundary
30 MTRS D P ROAD
West boundary
9 MTRS COLONY ROAD
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 878m away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 605 mPrimary road 276 mNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Canal 1.2 kmRiver 2.0 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Nashik Municipal Corporation

Municipal Corporation
Building Permit
Survey no. PLOT NO.54 S.N. 576/1
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Nashik Municipal Corporation

Municipal corporation

Has approved 821 RERA projectsabout 1 in 24 in Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
692
On record
4,331 flats · 111 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.