HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
9
Buildings
2
Parking
93 spaces
Land area
926 sq m
Sanctioned built-up
2,867 sq m

Timeline

RERA registeredSep 2021
Proposed completionMay 2024
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

SAMRUDDHI DEVELOPERS

PartnershipPromoter type
Nashik, MAHARASHTRABased in
20Projects
11Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
511 homeson the public record across 20 projects
34,990 sq mbuilt-up filed
1,45,854 sq mplotted area
1,66,733 sq mland declared
₹50.80 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Pimpri Chinchwad Municipal CorporationMunicipal Corporation3 of 9 projects
BMRDA - Bangalore Metropolitan Region Development AuthorityUrban Development Authority1 of 9 projects
City & Industrial Development Corporation Of Maharashtra Limited1 of 9 projects
Hospete Urban Development AuthorityUrban Development Authority1 of 9 projects
Local Planning AuthorityTown & Country Planning (DTCP)1 of 9 projects
Nashik Municipal CorporationMunicipal Corporationthis project1 of 9 projects
Nashik Municipal Corporation NashikMunicipal Corporation1 of 9 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Nashik (M Corp.)
Taluka
Nashik
District
Nashik
Pincode
422008
Survey no.
SR NO 761/6/1/1 TO 5A/1/3 TO 7 AND 12 TO 16
North boundary
9 MTR ROAD
East boundary
9 MTR ROAD
South boundary
PLOT NO 3 TO 7 12 TO 16A PLOT NO 3 TO 7 12 TO 16B
West boundary
PLOT NO 17
What’s nearby
Schools1 school within 500m
HealthcareHospital 774m away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 987 m · Trimbak RoadPrimary road 550 m · Canal Link RoadNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 410 m · Nasardi
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Nashik Municipal Corporation

Municipal Corporation
Building Permit
Survey no. SR NO 761/6/1/1 TO 5A/1/3 TO 7 AND 12 TO 16

The promised possession date (25 May 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Nashik Municipal Corporation

Municipal corporation

Has approved 821 RERA projectsabout 1 in 24 in Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
692
On record
4,331 flats · 111 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.