HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
2
Parking
54 spaces
Land area
1,885 sq m
Sanctioned built-up
2,237 sq m

Timeline

RERA registeredFeb 2024
Proposed completionDec 2026
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Water Supply50%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Landscaping & Tree…100%
Water conservation…100%
Electrical meter r…100%
Open Parking100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SHUBH BUILDERS

PartnershipPromoter type
Thane, MAHARASHTRABased in
6Projects
4Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
288 homeson the public record across 6 projects
18,046 sq mbuilt-up filed
11,748 sq mland declared
₹52.06 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Jamnagar Municipal CorporationMunicipal / Corporation1 of 4 projects
Others1 of 4 projects
Pethapur MunicipalityMunicipal / Corporation1 of 4 projects
Rajkot Municipal CorporationMunicipal / Corporation1 of 4 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Badlapur (M Cl)
Taluka
Ambarnath
District
Thane
Pincode
421503
Survey no.
Gut No 87, Hissa No 1
North boundary
Sant Birambhai Maharaj Hall
East boundary
Gut No 95 and 87-2
South boundary
Gut No 86
West boundary
Nana Amrita Vaidya Hospital
What’s nearby
SchoolsNo schools within 2km · Library 1.0km away
HealthcareHospital 847m away · Clinic within 2km
LifestylePark 1.3km away
ShoppingNo supermarket within 2km
Getting around
Primary road 224 mRailway line 1.4 km · Mumbai-Pune RailwayRailway station 1.7km away (Badlapur)Limited bus connectivity nearby
Water & environment
Water body 683 mRiver 793 m · Ulhas
distances only — not a flood assessment
Legal & regulatory record
Litigation1 case on record, earliest 2024
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 1 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.