HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
6
Buildings
14
Parking
89 spaces
Land area
4,788 sq m
Sanctioned built-up
8,424 sq m

Timeline

RERA registeredDec 2022
Proposed completionOct 2026
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Street Lighting0%
Internal Roads & F…50%
Water Supply50%
Sewerage (Chamber,…60%
Landscaping & Tree…60%
Water conservation…60%
OC-readiness80%
Open Parking90%
Excavation100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Stairs & lifts100%
External finishes100%
Flat fit-out801%
Plinth1000%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

AJAY BUILDERS AND ASSOCIATES DAUND

PartnershipPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2022–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Daund (M Cl)
Taluka
Daund
District
Pune
Pincode
413801
Survey no.
S.NO.181/1B/181/2/1/PLOT/5,7,8
North boundary
KHALADKAR PLOT AND ROAD
East boundary
JIVRAJ G PAWAR PLOT
South boundary
ROAD
West boundary
BAGWAN PLOT
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 21m away · 2 clinics within 1km
LifestyleNo parks within 2km
ShoppingSupermarket 1.4km away · Bank 481m away
Getting around
Expressway 1.2 kmPrimary road 108 m · Baramati Daund RoadRailway line 318 mRailway station 584m away (Daund Junction)Limited bus connectivity nearby
Water & environment
River 756 m · BhimaWater body 1.1 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Daund Municipal Council

Municipal Council
Building Permit
Survey no. S.NO.181/1B/181/2/1/PLOT/5,7,8
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation

A city municipal corporation that sanctions projects within its own limits. It has approved 12,653 RERA projects across 34 districts about 1 in 2 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.