17 on filequarterly progress reports filed with RERA
Timeline
RERA registeredJan 2022
Proposed completionNov 2026
TodaySep 2026
Construction progress
61% overall, as filed
Storm Water Drains0%
Street Lighting0%
Water Conservation Rain Water Harvesting0%
Treatment And Disposal Of Sewerage And Sullage Wat42%
Sewerage46%
Water Supply67%
Internal Roads And Footpaths83%
Landscaping And Tree Planting100%
Boundary Wall100%
Temple & Gate100%
From the builder's latest quarterly progress report filed with RERA Chhattisgarh — % complete overall and per infrastructure work, as of that filing. A dated snapshot, not a live tracker.
Find your plot
Filed by type and size, in the batches the builder registered — not a per-plot listing. Look yours up.
97 plots across 57 batches
TypeArea sq mCount
Plot9332
Plot931
Plot1391
Plot1141
Plot1111
Plot1111
Plot1101
Plot1091
Plot1081
Plot991
Plot1115
Plot1201
Plot1121
Plot1091
Plot1131
Plot1191
Plot1211
Plot1221
Plot1221
Plot1181
Plot931
Plot891
Plot871
Plot851
Plot1191
Plot1351
Plot1101
Plot1091
Plot1091
Plot1081
Plot1071
Plot741
Plot751
Plot721
Plot681
Plot641
Plot731
Plot1111
Plot1091
Plot863
Plot611
Plot482
Plot471
Plot472
Plot471
Plot471
Plot471
Plot471
Plot491
Plot481
Plot472
Plot471
Plot491
Plot501
Plot3471
Plot471
Plot491
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each size exist, not how many are still unsold (this state's filing carries no booking count).
Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.
Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Expressway 1.9 km · Durg Bypass RoadPrimary road 3.9 kmRailway line 4.8 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 799 mRiver 1.2 km · ShivnathCanal 5.0 km
distances only — not a flood assessment
Land, title & encumbrance
Mortgage9 unit(s) declared under mortgage to a bank/lender for project finance
As declared by the builder at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Price analysisdeclared build cost — not a sale price
₹5.16 Cr declared to build 97 plots. What that works out to:
₹5.32 Lakhdeclared cost per plotall-in — land + construction
46%of the cost is land
This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Location & price analysis — done
04
Government Guidance Rate
Chhattisgarh registration department
In Chhattisgarh it’s called the collector guideline rate.
No government guidance rate is shown for this project.
Chhattisgarh's government guidance rates aren't in Horizon's record yet.
That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.
Government Guidance Rate — done
05
Complaints & litigation
RERA Chhattisgarh · public record
Complaints, as the builder reports them
None in the builder’s latest quarterly return to RERA Chhattisgarh.
The builder’s own count of grievances it received — not RERA Chhattisgarh’s register, which isn’t published. Cases the builder declares are listed below.
What the builder declared
Declared to RERA Chhattisgarh
Litigation
None declared in this filing
Only what the builder declared, or what RERA Chhattisgarh records itself, can appear here — a case filed elsewhere and never declared would not.
Not a verdict. A complaint can be dismissed and a case can be won; an order can be appealed.
Not a clean bill. An empty record means nothing was filed with RERA Chhattisgarh, or that this register doesn’t publish it — never that nothing happened.
Complaints & litigation — done
06
Other projects nearby
The register · within 25 km
61 plotted projects still under way within 25 km. Step out ring by ring:
Of the 36 projects the radar draws within 6 km — every kind, every stage — 5 are plotted projects still under way. This list keeps only those, and looks further out.