12 on filequarterly progress reports filed with RERA
Timeline
RERA registeredJan 2023
Proposed completionJan 2028
TodaySep 2026
Construction progress
96% overall, as filed
Internal Roads And Footpaths0%
Water Supply0%
Sewerage0%
Storm Water Drains0%
Landscaping And Tree Planting0%
Street Lighting0%
Open Parking0%
Water Conservation Rain Water Harvesting0%
Boundary Wall0%
From the builder's latest quarterly progress report filed with RERA Chhattisgarh — % complete overall and per infrastructure work, as of that filing. A dated snapshot, not a live tracker.
Find your flat
Filed by type and size, in the batches the builder registered — not a per-flat listing. Look yours up.
522 units across 1 batch
TypeArea sq mCount
1BHK30522
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).
Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.
Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
HealthcareHospital 683m away · 2 clinics within 1km
LifestylePark 2.0km away
ShoppingNo supermarket within 2km
Getting around
Expressway 2.5 km · Durg Bypass RoadPrimary road 810 mRailway line 1.8 kmRailway station 2.8km away (Durg Junction)Limited bus connectivity nearby
Water & environment
Water body 250 mRiver 1.5 km
distances only — not a flood assessment
Land, title & encumbrance
Mortgage522 unit(s) declared under mortgage to a bank/lender for project finance
As declared by the builder at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Price analysisdeclared build cost — not a sale price
₹25.12 Cr declared to build 522 flats. What that works out to:
₹4.81 Lakhdeclared cost per flatall-in — land + construction
0%of the cost is land
This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Location & price analysis — done
04
Satellite view of the site
Google Open Buildings, 2016–2023 · Sentinel-2 imagery
A building already stood within ~40 m of the recorded location in 2020 — before this project started in 2023. The yearly view ends in 2023, so it does not cover this project's own construction; see the 2026 image.
Satellite view, year by year
loading 2023…
Height estimated by a model from satellite imagery — not a survey, and the series ends in 2023. The dashed shape is within ~40 m of the filed location.
Satellite photographs of the same ground
Jan 2017Jan 2023Mar 2026
Sentinel-2, 10 m per pixel — about 400 m of ground across. Each frame is one dry-season day, so haze can dull a site.
How to read this
A building is first visible in 2020.
This state publishes a point, not a plot outline, so the shape is a circle around it. A neighbour’s building can fall inside.
The location could only be checked loosely, so read this site view as indicative rather than as a statement about this project.
Site is a ~40 m circle around the RERA point, not a plot outline: buildings inside it may belong to neighbours.
Coordinate checked only against its district, not its pincode.
The yearly site view ends in 2023, before this project started in 2023.
Google Open Buildings 2.5D Temporal (CC BY 4.0) · Contains modified Copernicus Sentinel data 2017–2026
Satellite view of the site — done
05
Government Guidance Rate
Chhattisgarh registration department
In Chhattisgarh it’s called the collector guideline rate.
No government guidance rate is shown for this project.
Chhattisgarh's government guidance rates aren't in Horizon's record yet.
That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.
Government Guidance Rate — done
06
Complaints & litigation
RERA Chhattisgarh · public record
Complaints, as the builder reports them
None in the builder’s latest quarterly return to RERA Chhattisgarh.
The builder’s own count of grievances it received — not RERA Chhattisgarh’s register, which isn’t published. Cases the builder declares are listed below.
What the builder declared
Declared to RERA Chhattisgarh
Litigation
None declared in this filing
Only what the builder declared, or what RERA Chhattisgarh records itself, can appear here — a case filed elsewhere and never declared would not.
Not a verdict. A complaint can be dismissed and a case can be won; an order can be appealed.
Not a clean bill. An empty record means nothing was filed with RERA Chhattisgarh, or that this register doesn’t publish it — never that nothing happened.
Complaints & litigation — done
07
Other projects nearby
The register · within 25 km
60 residential projects still under way within 25 km. Step out ring by ring:
Of the 96 projects the radar draws within 6 km — every kind, every stage — 22 are residential projects still under way. This list keeps only those, and looks further out.
8 projects between 1 and 3 km — showing the nearest 6.
1.8 km awayGroup Housing
UTOPIA TOWNSHIP PROJECT PHASE-4 (VILLa)
LAxmi associates · Durg
4 yr 10 mo
Apr 2026registered
Feb 2031target completion
⚠ no escrow declaredDeclared cost₹4.71 CrScale8 flatsAuthorityRERA Chhattisgarh
Building footprint and height by year: Google Open Buildings 2.5D Temporal (CC BY 4.0), a model estimate of building presence and height from satellite imagery.
Photographs: Copernicus Sentinel-2 imagery (contains modified Copernicus Sentinel data 2017–2026).
05Government Guidance Rate
No government guidance rate could be matched to this project from Chhattisgarh's published schedules.
06Complaints & litigation
RERA Chhattisgarh's public record lists no complaints or litigation for this project.
07Other projects nearby
The RERA-registered projects Horizon holds within 25 km of these coordinates.
Compiled by Horizon from public records. Each fact is reproduced as its source publishes it, and Horizon does not verify filings on the ground. The live record: gethorizon.in/projects/pmay-of-522-dus-at-saraswati-nagar-durg-durg-q6wdsd27.
Horizon does not rate, review, score or signal, and it gives no verdict, opinion or forecast. Its only aim is to seek the truth through data: what the public record says, where each fact comes from, and where the record is silent. Nothing in this document is legal, financial or investment advice; what to make of it is yours to decide.