Complete project overview

RERA Madhya Pradesh · Registration filing
Plots
157 plots
Unit mix
43 × C Type (92.93) Plot · 41 × F Type (74.34) Plot · 15 × Irregular Type Plot · 13 × Ews Type Plot · 11 × B Type (102.23) Plot · 8 × A Type (111.52) Plot
Revised completion
30 Dec 2020extended after an approved RERA extension
Extensions
2 approved · Covid19completion-date extension(s) granted by RERA
Quarterly reports
1 on file · latest Oct 2019 - Dec 2019quarterly progress certificates filed with RERA

Timeline

Project startedAug 2016
RERA registeredOct 2019
Proposed completionMar 2020
TodayJul 2026

Find your plot

Filed by type and size, in the batches the promoter registered — not a per-plot listing. Look yours up.

157 plots across 11 batches
TypeArea sq mCount
A Type (111.52) Plot8
B Type (102.23) Plot11
C Type (92.93) Plot43
D Type (83.64) Plot7
E Type (75.27) Plot3
F Type (74.34) Plot41
G Type (69.70) Plot4
H Type (57.62) Plot4
Irregular Type Plot15
Lig Type Plot8
Ews Type Plot13

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each size exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RERA Madhya Pradesh · Promoter registration

ASHOK KUMAR

IndividualPromoter type
6Projects
3Cities
2019–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
566 plotson the public record across 6 projects
7,030 sq mplotted area
7,030 sq mland declared
₹28.68 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
NarmadapuramTown & Country Planning (DTCP)this project3 of 6 projects
Urban Improvement TrustUrban Improvement Trust2 of 6 projects
Nagar PalikaMunicipal Council1 of 6 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Madhya Pradesh · Registration filing
District
Narmadapuram
Tehsil
Narmadapuram
Planning area
Narmadapuram
Address
Khasra No. 92/2, 94/1, 98/2, 98/5, 98/6 and 107/2, at Village : Budhwara, Hoshangabad. Distt. : HOSHANGABAD
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.6km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 4.5 kmPrimary road 1.2 kmRailway line 856 mRailway station 4.3km away (Powerkheda)Limited bus connectivity nearby
Water & environment
Canal 731 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹9.00 Cr declared to build 157 plots. What that works out to:

₹5.73 Lakhdeclared cost per plotall-in — land + construction
63%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Madhya Pradesh · Approved building plan

Narmadapuram

Town & Country Planning (DTCP)
Layout Permit

The promised possession date (31 Mar 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Narmadapuram

Town & Country Planning area · Narmadapuram district

Has approved 107 RERA projects2% of Madhya Pradesh.

a plotted-layout market11% apartments · 89% plotted layouts. Your plotted layout is this body's core business.

Builders
84
On record
788 flats · 10,849 plots
Reach
7 tehsils
Since
2017

More layout-heavy than Madhya Pradesh overall — 89% plots here vs 72% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Complaints — RERA Madhya Pradesh does not publish a complaints register. This read cannot speak to them either way.