01

Complete project overview

MahaRERA · Registration filing
Floors
6
Buildings
2
Parking
35 spaces
Land area
476 sq m
Sanctioned built-up
1,750 sq m

Timeline

RERA registeredOct 2022
Proposed completionJul 2027
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Water conservation…0%
Flat fit-out33%
External finishes33%
Internal finishes50%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
Stairs & lifts100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Nandkumar Dasharath Mali

IndividualPromoter type
Kolhapur, MAHARASHTRABased in
1Projects
1City
2022–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Gargoti
Taluka
Bhudargad
District
Kolhapur
Pincode
416209
Survey no.
C S No 1281 Grampanchayat milkat No 1570 1571 1572
North boundary
C S No 1282
East boundary
C S No 1280
South boundary
Road and C S No 1327
West boundary
C S No 1309 and 1310
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 192m away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 257 mNo metro or railway within 5kmBus stop within 1km
Water & environment
River 522 m · VedagangaWater body 1.0 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Gargoti Grampanchayat And Town Planning Authority Kolhapur

Gram Panchayat
Building Permit
Survey no. C S No 1281 Grampanchayat milkat No 1570 1571 1572
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.