HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
6
Parking
20 spaces
Land area
401 sq m
Sanctioned built-up
1,003 sq m

Timeline

RERA registeredApr 2024
Proposed completionSep 2028
TodayJul 2026
Construction progress
Podiums0%
Flat fit-out0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Landscaping & Tree…0%
Treatment And Disp…0%
Fire protection an…0%
Electrical meter r…0%
External finishes12%
Stairs & lifts45%
Internal finishes75%
Basement (if any)90%
Plinth90%
Excavation100%
Stilt floor100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

LAXMINARAYAN CONSTRUCTION

PartnershipPromoter type
Sindhudurg, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Sawantwadi (M Cl)
Taluka
Sawantwadi
District
Sindhudurg
Pincode
416510
Survey no.
S NO 161/A/1/A/23/A 161/A/1/A/23/B 161/A/1/A/29 CTS NO 2020 2021
North boundary
CTS NOS 2015 2018 2019
East boundary
CTS NO 2005
South boundary
MUNICIPAL ROAD
West boundary
CTS NO 2022
What’s nearby
SchoolsNo schools within 2km · College or university 369m away
HealthcareHospital 620m away · 1 clinic within 1km
LifestylePark 817m away
ShoppingNo supermarket within 2km · Mall 657m away · Bank 193m away
Getting around
Expressway 528 mPrimary road 673 mNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 362 m · Moti TalaoRiver 426 m
distances only — not a flood assessment
Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.