Complete project overview

MahaRERA · Registration filing
Floors
13
Buildings
2
Parking
63 spaces
Land area
737 sq m
Sanctioned built-up
1,783 sq m

Timeline

RERA registeredMar 2021
Proposed completionApr 2023
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Street Lighting0%
Open Parking0%
OC-readiness95%
Fire protection an…97%
Electrical meter r…97%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
Water Supply100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Solid Waste Manage…100%
Water conservation…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

White Water Developers

PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2021–2023Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Borivali
Taluka
Borivali
District
Mumbai Suburban
Pincode
400104
Survey no.
353
North boundary
Vivek College Road
East boundary
Plot No 9
South boundary
Open MHADA land
West boundary
Vivek College
What’s nearby
Schools1 school within 500m · 3 educational institutions within 1km · College or university 1.7km away
HealthcareHospital 343m away · 9 clinics within 1km · Doctor's clinic within 1km
LifestylePark 603m away · 7 restaurants and cafes within 1km
ShoppingSupermarket 357m away · Mall 272m away · Bank 78m away
Getting around
Expressway 1.4 km · Western Express HighwayPrimary road 174 m · Swami Vivekanand RoadRailway line 526 mRailway station 741m away (Goregaon)4 bus stops within 500m
Water & environment
River 678 m · Oshiwara RiverWater body 693 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Maharashtra Housing and Area Development Authority (MHADA)

Housing Authority
Building Permit
Survey no. 353

The promised possession date (30 Apr 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Maharashtra Housing and Area Development Authority (MHADA)

Planning authority

Has approved 438 RERA projects2.2% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
341
On record
13,458 flats · 0 plots
Reach
18 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
Compliance1 non-compliance notice on record
Appeals2 appeals before the tribunal
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

3 complaints on MahaRERA’s register for this project 3 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.