Complete project overview

MahaRERA · Registration filing
Floors
9
Buildings
2
Land area
2,160 sq m
Sanctioned built-up
359 sq m
Recreational open space
177 sq m

Timeline

RERA registeredNov 2017
Proposed completionDec 2019
TodayJul 2026
Construction progress
Podiums0%
Stilt floor0%
Excavation100%
Basement (if any)100%
Plinth100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Internal Roads & F…100%
Water Supply100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Landscaping & Tree…100%
Street Lighting100%
Treatment And Disp…100%
Solid Waste Manage…100%
Water conservation…100%
Energy managemcnt100%
Fire protection an…100%
Electrical meter r…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

BHOSALETUPE DVELOPERS

PartnershipPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2017–2019Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Hadapsar
Taluka
Haveli
District
Pune
Pincode
411028
Survey no.
SURVEY NO 4A/3A/1B/1, 3A/2/1, 3A/2/2, 3B, 3C/2, 3D/2 AND 3E
North boundary
PART OF SURVEY NO 4A
East boundary
SURVEY NO 5
South boundary
PART OF SURVEY NO 4A
West boundary
15 MTRS D P ROAD
What’s nearby
SchoolsNearest school 1.3km away · College or university 1.8km away · Library 885m away
HealthcareHospital 227m away · 10 clinics within 1km
LifestylePark 1.0km away · Gym or sports centre 1.2km away · 5 restaurants and cafes within 1km
ShoppingSupermarket 1.3km away · Bank 446m away
Getting around
Expressway 395 m · Shree Sant Dnyaneshwar Maharaj and Shree Sant Tukaram Maharaj FlyoverPrimary road 414 m · Solapur RoadRailway line 1.5 km · Pune - Miraj Railway LineMetro station 1.4km away (Hadapsar)Bus stop within 500m
Water & environment
Canal 325 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pimpri Chinchwad Municipal Corporation

Municipal Corporation
Building Permit
Survey no. SURVEY NO 4A/3A/1B/1, 3A/2/1, 3A/2/2, 3B, 3C/2, 3D/2 AND 3E

The promised possession date (31 Dec 2019) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pimpri Chinchwad Municipal Corporation

Municipal corporation

Has approved 1,391 RERA projectsabout 1 in 14 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,080
On record
9,009 flats · 249 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.