Complete project overview

GujRERA · Registration filing
Units
112 units
Mix
112 × Residential
Carpet area
83–138 sq mper-unit range, as filed
Blocks
3
Parking
106 spaces
Land area
2,984 sq m

Timeline

Project startedJun 2018
RERA registeredAug 2019
Proposed completionSep 2023
TodayJul 2026
Construction progress

88% overall, as filed

Overall % complete as filed with GujRERA, taken as the slowest of the project's blocks — a snapshot, not a live tracker. Where a BU permission is on record (section 04), that is the firmer completion signal.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

112 units across 1 batch
TypeArea sq mCount
Residential99112

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

GujRERA · Promoter registration

SHREERAM INFRASTUCTURE

PARTNERSHIP FIRMPromoter type
Ahmedabad, GujaratBased in
4Projects
1City
2017–2025Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
304 homeson the public record across 4 projects
17,154 sq mbuilt-up filed
9,865 sq mland declared
₹119.28 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Ahmedabad Municipal CorporationMunicipal / Corporationthis project2 of 4 projects
Ahmedabad Urban Development AuthorityUrban Development Authority2 of 4 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

GujRERA · Registration filing
Taluka
Ahmedabad City
District
Ahmedabad
Pincode
380007
Address
Near Chandranagar BridgeP.T. college road , Paldi
What’s nearby
Schools1 school within 1km
HealthcareHospital 346m away · Clinic within 2km
LifestylePark 1.8km away · Gym or sports centre 1.6km away
ShoppingNo supermarket within 2km · Bank 757m away
Getting around
Primary road 60 m · Doctor Ambedkar BridgeRailway line 2.1 kmMetro station 4.2km away (Gheekanta)Bus stop within 500m
Water & environment
River 504 m · Sabarmati RiverWater body 767 m
distances only — not a flood assessment
Land, title & encumbrance
MortgageLoan outstanding · ₹24.09 Cr outstanding
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Price analysisdeclared build cost — not a sale price

₹43.07 Cr declared to build 112 flats. What that works out to:

₹38.46 Lakhdeclared cost per flatall-in — land + construction
74%of the cost is land₹9,902/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

GujRERA · Approved building plan

Ahmedabad Municipal Corporation

Municipal / Corporation
Building Permitapproved 21 Aug 2019 · 6 yrs ago

The promised possession date (30 Sep 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Ahmedabad Municipal Corporation

Municipal Corporation

Has approved 3,250 RERA projectsabout 1 in 5 in Gujarat, more than any other body in the state.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
2,712
On record
4,25,177 flats · 633 plots
Reach
6 talukas
Since
2007

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Complaints — GujRERA does not publish a complaints register. This read cannot speak to them either way.