HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
5
Buildings
2
Parking
107 spaces
Land area
1,000 sq m
Sanctioned built-up
1,016 sq m

Timeline

RERA registeredJan 2026
Proposed completionDec 2028
TodayJul 2026
Construction progress
Stilt floor0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Superstructure8%
OC-readiness20%
Excavation100%
Basement (if any)100%
Plinth100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Soham Associates

PartnershipPromoter type
Pune, MAHARASHTRABased in
3Projects
3Cities
2019–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
48 homeson the public record across 3 projects
27,547 sq mbuilt-up filed
8,053 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Pimpri Chinchwad Municipal CorporationMunicipal Corporationthis project1 of 2 projects
Pune Municipal CorporationMunicipal Corporation1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Pimple Nilakh
Taluka
Haveli
District
Pune
Pincode
411027
Survey no.
Sr.No. 6/2/1/2/2A (Pai), CTS No. 737 (Pai), Plot No. A
North boundary
By remaining property out of Survey No. 6/2/1/2/2A
East boundary
By remaining property out of Survey No. 6/2/1/2/2A and Road
South boundary
By 12 mtrs. wide road which is given by Nandgude family to M/s Soham Associates vide Agreement and thereafter 12 mtrs. wide D.P. road
West boundary
By 9 mtrs. wide road and Property of Sahil Heights Society
What’s nearby
Schools1 school within 1km · Library 1.8km away
HealthcareHospital 687m away · 1 clinic within 1km
LifestyleNo parks within 2km · Gym or sports centre 1.3km away
ShoppingSupermarket 1.3km away · Mall 1.5km away · Convenience store within 1km
Getting around
Expressway 2.6 kmPrimary road 1.1 km · Aundh Ravet RoadRailway line 4.5 km · Mumbai–Pune RailwayMetro station 1.7km away (Balewadi Phata)2 bus stops within 500m
Water & environment
River 551 m · Mula
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pimpri Chinchwad Municipal Corporation

Municipal Corporation
Building Permit
Survey no. Sr.No. 6/2/1/2/2A (Pai), CTS No. 737 (Pai), Plot No. A
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pimpri Chinchwad Municipal Corporation

Municipal corporation

Has approved 1,391 RERA projectsabout 1 in 14 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,080
On record
9,009 flats · 249 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.