Timeline

Project startedOct 2017
Proposed completionJun 2021
RERA registeredFeb 2022
TodayJul 2026
Construction progress

87% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation100%
Basement(s) and Plinth100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

0 of 30 available
TypeArea sq mAvailable
2BHK590 of 10
3BHK900 of 10
3BHK840 of 10

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

Silver Castle Construction Company Pvt Ltd

CompanyPromoter type
Thiruvananthapuram, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
3Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
75 homes · 9 plotson the public record across 3 projects
14,208 sq mbuilt-up filed
2,151 sq mplotted area
5,076 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
PATHIRAPPALLI
Village
KUDAPPANAKUNNU
Taluk
THIRUVANANTHAPRUAM
District
Thiruvananthapuram
Pincode
695044
Survey no.
43/12, 44/6
Patta no.
34427
What’s nearby
SchoolsNearest school 1.2km away · College or university 1.1km away · Library 1.2km away
HealthcareHospital 255m away · Clinic within 2km · Pharmacy within 500m
Lifestyle1 park within 500m · Gym or sports centre 1.4km away · 9 restaurants and cafes within 1km
ShoppingSupermarket 269m away · Mall 1.5km away · Bank 207m away
Getting around
Primary road 1.2 km · Thiruvanathapuram - Thenmala RoadNo metro or railway within 5km4 bus stops within 500m
Water & environment
Water body 347 m · Krishibhavan kulamRiver 1.3 km · Killi River
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Thiruvananthapuram Municipal Corporation

Municipal Corporation
approved 28 Jul 2016 · 10 yrs ago
Building Permit no. 118/16-17Survey no. 43/12, 44/6

The promised possession date (30 Jun 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 118/16-17 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Thiruvananthapuram Municipal Corporation

Municipal corporation / municipality

Has approved 224 RERA projectsabout 1 in 7 in Kerala, more than any other body in the state.

an apartments market91% apartments · 9% plotted layouts. Apartments like yours are this body's core business.

Builders
90
On record
12,045 flats · 635 plots
Since
2021

More apartment-heavy than Kerala overall — 91% apartments here vs 81% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.