HORIZONMarkets
01

Complete project overview

K-RERA · Registration filing
Units
62 units
Mix
32 × 3BHK · 23 × 2BHK · 7 × 1BHK
Booked
36 of 62 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
2,995 sq m
Floor area
5,955 sq m
Description
SILVER SPRINGS

Timeline

Project startedMay 2017
RERA registeredMay 2021
Proposed completionJun 2021
TodayJul 2026
Construction progress

88% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

26 of 62 available
TypeArea sq mAvailable
1BHK501 of 7
3BHK8213 of 16
2BHK601 of 8
2BHK610 of 9
3BHK7710 of 16
2BHK601 of 6

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

PVS Builders & Developers

PartnershipPromoter type
Kozhikode, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
5Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
330 homeson the public record across 5 projects
44,269 sq mbuilt-up filed
16,079 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Edakkad Grama PanchayatGrama Panchayat1 of 5 projects
Kannur Municipal CorporationMunicipal Corporation1 of 5 projects
Kannur Municipal Corporation Elayavoor ZonalLocal body (LSGI)1 of 5 projects
Kozhikode Municipal CorporationMunicipal Corporation1 of 5 projects
Perumanna Grama PanchayatGrama Panchayatthis project1 of 5 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
CHEMMALTHOOR
Village
PERUMANNA
Taluk
Kozhikode
District
Kozhikode
Pincode
673008
Survey no.
49/2,30/4C
Patta no.
12663
What’s nearby
Schools1 school within 1km · College or university 1.2km away
HealthcareHospital 1.2km away · Clinic within 2km
LifestyleNo parks within 2km · Gym or sports centre 1.8km away
ShoppingSupermarket 1.3km away
Getting around
Expressway 4.0 km · Kannur-Calicut-Valanchery HighwayPrimary road 4.8 km · Medical College Karanthur RoadNo metro or railway within 5kmBus stop within 1km
Water & environment
Water body 616 m · Chenam KulamRiver 1.5 km · Kallai River
distances only — not a flood assessment
04

Planning authority

K-RERA · Approved building plan

Perumanna Grama Panchayat

Grama Panchayat
approved 20 May 2016 · 10 yrs ago
Building Permit no. A3-1893/16-BL-720/15-16Survey no. 49/2,30/4C

The promised possession date (30 Jun 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan A3-1893/16-BL-720/15-16 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Grama Panchayat

A village-level local self-government (LSGI) that issues the permit — Kerala's most common approving body. It has approved 268 RERA projects across 13 districts about 1 in 6 in Kerala.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.