HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
30 units
Unit mix
20 × 2BHK, 10 × 3BHK
Saleable area
83–113 sq mper unit, as filed
Floors
5
Land area
1,357 sq m
Built-up area
3,103 sq m

Timeline

RERA approvedOct 2019
Proposed completionOct 2025
TodayJul 2026
Construction progress

0% overall, as filed

Excavation0%
Basement & plinth0%
Podiums0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

30 of 30 available
BuildingFloorTypeArea sq mAvailable
SAI MEADOWS12BHK832 of 2
SAI MEADOWS12BHK832 of 2
SAI MEADOWS13BHK1132 of 2
SAI MEADOWS22BHK832 of 2
SAI MEADOWS23BHKmortgaged1132 of 2
SAI MEADOWS22BHKmortgaged831 of 1
SAI MEADOWS22BHK831 of 1
SAI MEADOWS32BHK832 of 2
SAI MEADOWS32BHK832 of 2
SAI MEADOWS33BHK1132 of 2
SAI MEADOWS42BHK832 of 2
SAI MEADOWS42BHK832 of 2
SAI MEADOWS43BHK1132 of 2
SAI MEADOWS52BHK832 of 2
SAI MEADOWS52BHK832 of 2
SAI MEADOWS53BHK1132 of 2

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

SKT CONSTRUCTIONS AND DEVELOPERS

PartnershipPromoter type
Khammam, TelanganaBased in
5Projects
4Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
490 homeson the public record across 5 projects
55,973 sq mbuilt-up filed
32,029 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
PALAKOYA THANDA
Village
PALAKOYATHANDA
Mandal
Palwancha Mandal
District
Bhadradri Kothagudem
Pincode
507115
North boundary
40 WIDTH ROAD
East boundary
30 WIDTH ROAD
South boundary
33 WIDTH ROAD
West boundary
PLOT NO 54 AND 71
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
No metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 2.3 km
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Directorate of Town & Country Planning (DTCP)

Town & Country Planning (DTCP)
Building Permit no. 3022/W16/2018/0792Survey no. 444/17 & 444/18

The promised possession date (28 Oct 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 3022/W16/2018/0792 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

DTCP

Town & Country Planning · towns & district HQs across Telangana

Has approved 3,737 RERA projectsabout 1 in 3 in Telangana, more than any other body in the state.

a plotted-layout market32% apartments · 68% plotted layouts. Apartments like yours are the smaller share here — this body mostly approves plotted layouts.

Builders
2,933
On record
41,686 flats · 4,33,404 plots
Reach
287 mandals
Since
2012

More layout-heavy than Telangana overall — 68% plots here vs 34% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.