HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
13
Parking
95 spaces
Land area
1,003 sq m
Sanctioned built-up
3,511 sq m

Timeline

RERA registeredOct 2023
Proposed completionDec 2028
TodayJul 2026
Construction progress
Podiums0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Landscaping & Tree…0%
Treatment And Disp…0%
Fire protection an…0%
Electrical meter r…0%
GYMNASIUM0%
Internal finishes10%
Stairs & lifts20%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

M/S. METRO INFRA

PartnershipPromoter type
Nagpur, MAHARASHTRABased in
1Projects
1City
2023–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Nagpur (M Corp.)
Taluka
Nagpur (Urban)
District
Nagpur
Pincode
440008
Survey no.
Plot No 8, KH No 275, CTS 248, Sheet No 213, NMC House No 1525, Ward No 23
North boundary
30 MTRS WIDE ROAD
East boundary
PLOT NO 9
South boundary
9 MTRS WIDE ROAD
West boundary
PLOT NO 7
What’s nearby
SchoolsNearest school 1.6km away
HealthcareHospital 64m away · 3 clinics within 1km
LifestylePark 592m away
ShoppingSupermarket 1.6km away
Getting around
Expressway 471 mPrimary road 95 mRailway line 980 mMetro station 165m away (Ambedkar Square)Limited bus connectivity nearby
Water & environment
Water body 737 mRiver 743 m · Naag River
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Nagpur Municipal Corporation (Nmc)

Municipal Corporation
Building Permit
Survey no. Plot No 8, KH No 275, CTS 248, Sheet No 213, NMC House No 1525, Ward No 23
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Nagpur Municipal Corporation (Nmc)

Municipal corporation

Has approved 36 RERA projects0.2% of Maharashtra.

an apartments market97% apartments · 3% plotted layouts. Apartments like yours are this body's core business.

Builders
29
On record
0 flats · 31 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.