HORIZON
Share

Square One

P52100066518 · MahaRERA · https://gethorizon.in/projects/square-one-peth-haveli-g71230zr

01

Complete project overview

MahaRERA · Registration filing
Project name
Square One
Floors
7
Buildings
2
Parking
72 spaces
Land area
952 sq m
Sanctioned built-up
1,834 sq m

Timeline

RERA registeredJun 2024
Proposed completionDec 2028
TodaySep 2026
Construction progress
Excavation0%
Basement (if any)0%
Podiums0%
Plinth0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Landscaping & Tree…0%
Street Lighting0%
Solid Waste Manage…0%
Water conservation…0%
Electrical meter r…0%
Open Parking0%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

A Square Developer

PartnershipPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Peth
Taluka
Haveli
District
Pune
Pincode
411002
Survey no.
CTS. No. 710/A/11, F. Plot No. 375+377/10, Near BSNL Office, Gurunanak Nagar, Bhawani Peth, Tal. Haveli, Dist. Pune, Maharashtra-411 002
North boundary
By Public Road
East boundary
By Public Road
South boundary
By Plot No 377 oblique 9
West boundary
By Public Road
What’s nearby
Schools1 school within 500m · 4 educational institutions within 1km · College or university 429m away
HealthcareHospital 274m away · 6 clinics within 1km · Doctor's clinic within 1km
Lifestyle1 park within 500m · Gym or sports centre 892m away · Swimming pool within 2km
ShoppingSupermarket 1.1km away · Bank 352m away
Getting around
Expressway 176 m · Atal Bihari Vajpayee saheb FlyoverPrimary road 184 m · Jagannath Shankarsheth MargRailway line 2.6 kmMetro station 1.6km away (Swargate)2 bus stops within 500m
Water & environment
Canal 462 m · Mutha Right Bank Canal
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Maharashtra's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Pune Municipal Corporation Pune

Municipal Corporation
Building Permit
Survey no. CTS. No. 710/A/11, F. Plot No. 375+377/10, Near BSNL Office, Gurunanak Nagar, Bhawani Peth, Tal. Haveli, Dist. Pune, Maharashtra-411 002
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Pune Municipal Corporation Pune

Municipal corporation

Has approved 29 RERA projects0.1% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
24
On record
553 flats · 0 plots
Since
2020

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

3,182 residential projects still under way within 25 km. Step out ring by ring:

14 projects within 1 km — showing the nearest 6.

GultekadiResidential / Group Housing

Siddhi Vidyamrut

Bhairav Promoters Unit 3

Dec 2025registered
Dec 2029target completion
Government Guidance Rate₹87,793/sq ydScale22 flatsAuthorityMahaRERA
PuneResidential / Group Housing

Suyog Navkaar Building B

Suyog Development Corporation Unit 12 LLP

Dec 2022registered
Dec 2027target completion
Government Guidance Rate₹58,077/sq ydAuthorityMahaRERA
PuneOthers

Suyog Navkaar Phase I

Suyog Development Corporation Unit 12 LLP

Aug 2017registered
Dec 2026target completion
Government Guidance Rate₹58,077/sq ydScale141 flatsAuthorityMahaRERA
GultekadiMixed

MANSION

MANTRA PRIME PROPERTIES PRIVATE LIMITED

Sep 2026registered
Dec 2031target completion
Government Guidance Rate₹87,793/sq ydScale25 flatsAuthorityMahaRERA
SwargateResidential / Group Housing

EMERALD VISTA

PADMAVATI LANDMARKS

Jun 2024registered
Jun 2026target completion
Scale18 flatsAuthorityMahaRERA
GultekadiResidential / Group Housing

New Prasanna Park Co-op Housing Society Ltd.

Rahul Lifespaces LLP

Jun 2026registered
Jun 2031target completion
Government Guidance Rate₹87,793/sq ydScale64 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.