Complete project overview

RERA Telangana · Registration filing
Units
10 units
Unit mix
5 × 3BHK, 5 × 2BHK
Saleable area
95–131 sq mper unit, as filed
Floors
5
Land area
343 sq m
Built-up area
885 sq m

Timeline

RERA approvedFeb 2023
Proposed completionFeb 2026
TodayJul 2026
Construction progress

10% overall, as filed

Basement & plinth0%
Podiums0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Excavation100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

10 of 10 available
BuildingFloorTypeArea sq mAvailable
SRI BALAJI APARTMENTS13BHKmortgaged1311 of 1
SRI BALAJI APARTMENTS12BHKmortgaged951 of 1
SRI BALAJI APARTMENTS23BHK1311 of 1
SRI BALAJI APARTMENTS22BHK951 of 1
SRI BALAJI APARTMENTS33BHK1311 of 1
SRI BALAJI APARTMENTS32BHK951 of 1
SRI BALAJI APARTMENTS43BHK1311 of 1
SRI BALAJI APARTMENTS42BHK951 of 1
SRI BALAJI APARTMENTS53BHK1311 of 1
SRI BALAJI APARTMENTS52BHK951 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

MANASA SAROVAR CONSTRUCTIONS

PartnershipPromoter type
Hyderabad, TelanganaBased in
5Projects
3Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
60 homeson the public record across 5 projects
4,896 sq mbuilt-up filed
1,923 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
HIMAYATH NAGAR
Village
Nallakunta (Sultan Bazar)
Mandal
Himayatha Nagar
District
Hyderabad
Pincode
500044
North boundary
HOUSE ON PLOT NO 14
East boundary
PLOT NO 23
South boundary
40FT WIDE ROAD
West boundary
LINGAMPALLI GARDEN AND LANE
What’s nearby
Schools3 schools within 500m · 18 educational institutions within 1km · College or university 577m away
HealthcareHospital 87m away · 4 clinics within 1km · Pharmacy within 1km
LifestylePark 1.0km away · 27+ restaurants and cafes within 1km
ShoppingSupermarket 303m away · Mall 1.0km away · Bank 56m away
Getting around
Expressway 1.5 km · Public Garden RoadPrimary road 249 m · Baby NestRailway line 1.7 kmMetro station 631m away (Narayanaguda)2 bus stops within 500m
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit
Survey no. 15,16,17,18,19 AND 20

The promised possession date (10 Feb 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.