HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
10 units
Unit mix
10 × 3BHK
Saleable area
130 sq mper unit, as filed
Floors
5
Land area
418 sq m
Built-up area
1,123 sq m

Timeline

RERA approvedJan 2021
Proposed completionJan 2027
TodayJul 2026
Construction progress

60% overall, as filed

Podiums0%
Internal finishes0%
Flat fit-out0%
OC-readiness0%
Excavation100%
Basement & plinth100%
Stilt floor100%
Superstructure100%
Stairs & lifts100%
External finishes100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

9 of 10 available
BuildingFloorTypeArea sq mAvailable
GOPIS MANASA SAROVAR13BHKmortgaged1302 of 2
GOPIS MANASA SAROVAR23BHK1302 of 2
GOPIS MANASA SAROVAR33BHK1302 of 2
GOPIS MANASA SAROVAR43BHK1302 of 2
GOPIS MANASA SAROVAR53BHK1301 of 2

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

MANASA SAROVAR CONSTRUCTIONS

PartnershipPromoter type
Hyderabad, TelanganaBased in
5Projects
3Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
60 homeson the public record across 5 projects
4,896 sq mbuilt-up filed
1,923 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
JUDGES COLONY MALAKPET
District
Hyderabad
Pincode
500036
North boundary
H NO 16-2-145 3
East boundary
30FT WIDE ROAD
South boundary
H NO 16-2-145 5
West boundary
HOUSE ON PLOT NO 6
What’s nearby
Schools1 school within 500m · 5 educational institutions within 1km · College or university 724m away
HealthcareHospital 66m away · 1 clinic within 1km · Doctor's clinic within 1km
LifestylePark 1.1km away · 5 restaurants and cafes within 1km
ShoppingSupermarket 221m away · Bank 140m away · ATM within 500m
Getting around
Expressway 218 m · Vijaywada HighwayPrimary road 133 m · Government Press RoadRailway line 877 mMetro station 287m away (New Market)6 bus stops within 500m
Water & environment
River 829 mCanal 1.2 km
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit no. 2/C6/00484/2021
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 2/C6/00484/2021 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.