This project’s MahaRERA registration has lapsed— it expired and was not renewed. A lapsed project may be stalled, finished-but-not-updated, or abandoned; the record stops here and RERA’s ongoing protections may no longer apply. Confirm the current status directly with MahaRERA before you rely on anything below.

01

Complete project overview

MahaRERA · Registration filing
Units
55 units
Mix
26 × 2 BHK · 12 × Shop · 11 × Office · 5 × 1 BHK · 1 × 3 BHK
Carpet area
9–72 sq mper-unit range, as filed
Floors
8
Buildings
2
Land area
959 sq m
Sanctioned built-up
2,697 sq m

Timeline

RERA registeredJan 2022
Proposed completionJun 2024
TodayJul 2026

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

55 units across 35 batches
TypeArea sq mCount
2 BHK513
Office481
Shop361
1 BHK351
1 BHK353
Office321
Office211
Office451
Office411
2 BHK484
Shop391
2 BHK361
3 BHK721
2 BHK503
2 BHK503
Shop91
Shop191
Office201
2 BHK493
Office411
Shop162
Office481
Shop151
Office151
Office451
2 BHK561
2 BHK494
2 BHK551
Office371
2 BHK503
Shop142
1 BHK411
Shop151
Shop151
Shop131

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

MahaRERA · Promoter registration

SAMRUDDHI ENTERPRISES

PartnershipPromoter type
Thane, MAHARASHTRABased in
3Projects
2Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
111 homeson the public record across 3 projects
8,606 sq mbuilt-up filed
3,421 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Badlapur (M Cl)
Taluka
Ambarnath
District
Thane
Pincode
421503
Survey no.
S NO 46 , PLOT NO 11 AND 12
North boundary
7 MW ROAD
East boundary
MAHALAXMI PARK LAKE
South boundary
BHAGIRATHI GARDEN CHS
West boundary
7 MW ROAD
What’s nearby
SchoolsNearest school 1.4km away
HealthcareHospital 412m away · 3 clinics within 1km
LifestylePark 706m away
ShoppingNo supermarket within 2km
Getting around
Expressway 2.3 km · Ahilyanagar - Kalyan Road | Bhiwandi - Murbad Road | B K Birla RoadPrimary road 388 m · Kalyan Badlapur RoadRailway line 364 m · Mumbai-Pune RailwayRailway station 596m away (Ulhasnagar)Limited bus connectivity nearby
Water & environment
River 345 m · Waldhuni RiverWater body 602 m
distances only — not a flood assessment
Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

2 complaints on MahaRERA’s register for this project 1 disposed, 1 still open.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.