Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
2
Parking
142 spaces
Land area
1,516 sq m
Sanctioned built-up
5,482 sq m

Timeline

RERA registeredApr 2024
Proposed completionJan 2029
TodayJul 2026
Construction progress
Podiums0%
Stilt floor0%
Electrical meter r…0%
Open Parking0%
Flat fit-out85%
Treatment And Disp…90%
Sewerage (Chamber,…95%
Excavation100%
Basement (if any)100%
Plinth100%
Superstructure100%
Internal finishes100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Water Supply100%
Water conservation…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

ARVINDBHAI BAVCHANDBHAI RAKHOLIYA

IndividualPromoter type
Nashik, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Nashik (M Corp.)
Taluka
Nashik
District
Nashik
Pincode
422010
Survey no.
P NO 3+4+5 S NO 314/2B/3/4/5
North boundary
P NO 2
East boundary
OPEN SPACE AND P NO 06 07 08 09 10 11
South boundary
9 METER WIDE ROAD
West boundary
18 METER WIDE DP ROAD
What’s nearby
SchoolsNearest school 1.2km away · College or university 1.2km away
HealthcareHospital 722m away · Clinic within 2km
LifestylePark 1.3km away
ShoppingNo supermarket within 2km · Bank 957m away · ATM within 500m
Getting around
Expressway 2.7 km · Mumbai Agra HighwayPrimary road 159 m · Pathardi RoadNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 1.1 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Town Planning Nashik Municipal Corporation Nashik

Municipal Corporation
Building Permit
Survey no. P NO 3+4+5 S NO 314/2B/3/4/5
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation

A city municipal corporation that sanctions projects within its own limits. It has approved 12,653 RERA projects across 34 districts about 1 in 2 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.