Complete project overview

K-RERA · Registration filing
Units
32 units
Mix
16 × 3BHK · 16 × 2BHK
Booked
11 of 32 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
1,720 sq m
Floor area
3,949 sq m
Description
SUN ELLORA

Timeline

Project startedOct 2024
RERA registeredNov 2024
Proposed completionJun 2029
TodayJul 2026
Construction progress

2% overall, as filed

Basement(s) and Plinth0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Fire Fighting Fittings and Equipment0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps etc5%
Excavation25%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

21 of 32 available
TypeArea sq mAvailable
3BHK1,0102 of 4
3BHK1,0013 of 4
2BHK6312 of 4
3BHK9534 of 4
2BHK6373 of 8
2BHK7103 of 4
3BHK9524 of 4

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

SUN PROJECTS INDIA PRIVATE LIMITED

CompanyPromoter type
Thiruvananthapuram, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
5Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
238 homeson the public record across 5 projects
38,605 sq mbuilt-up filed
9,052 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Thiruvananthapuram Municipal CorporationMunicipal Corporationthis project4 of 5 projects
District PanchayathLocal body (LSGI)1 of 5 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
PRIYADARSHINI ROAD
Village
KAZHAKOOTTAM
Taluk
THIRUVANANTHAPRUAM
District
Thiruvananthapuram
Pincode
695582
Survey no.
266/32, 266/22
Patta no.
27297
What’s nearby
Schools1 school within 1km · College or university 1.4km away · Library 1.5km away
HealthcareHospital 58m away · 2 clinics within 1km · Doctor's clinic within 1km
LifestylePark 1.4km away · Gym or sports centre 684m away · 15+ restaurants and cafes within 1km
ShoppingSupermarket 148m away · Mall 264m away · Bank 290m away
Getting around
Expressway 7 m · Salem - Kochi - Kanyakumari RoadPrimary road 410 mRailway line 441 mRailway station 1.3km away (Kazhakuttam)4 bus stops within 500m
Water & environment
Water body 111 mCanal 249 mRiver 1.1 km
distances only — not a flood assessment
04

Planning authority

K-RERA · Approved building plan

Thiruvananthapuram Municipal Corporation

Municipal Corporation
approved 20 Sep 2024 · 1 yr ago
Building Permit no. BA/1003/27899/2024Survey no. 266/32, 266/22
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan BA/1003/27899/2024 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Thiruvananthapuram Municipal Corporation

Municipal corporation / municipality

Has approved 224 RERA projectsabout 1 in 7 in Kerala, more than any other body in the state.

an apartments market91% apartments · 9% plotted layouts. Apartments like yours are this body's core business.

Builders
90
On record
12,045 flats · 635 plots
Since
2021

More apartment-heavy than Kerala overall — 91% apartments here vs 81% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.