Complete project overview

RERA Bihar · Registration filing
Units
28 units
Unit mix
14 × 2 BHK · 14 × 3 BHK
Parking
28 spaces
Land area
1,000 sq m
Built-up area
2,507 sq m

Timeline

Project startedFeb 2017
RERA registeredJul 2018
Proposed completionDec 2020
TodayJul 2026

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

28 units across 2 batches
BuildingTypeArea sq mCount
SUNRISE SAI TOWER2 BHK014
SUNRISE SAI TOWER3 BHK014

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RERA Bihar · Promoter registration

Sunrise Sai Developers Pvt. Ltd.

CompanyPromoter type
Patna, BiharBased in
---Select---Also RERA-registered in
9Projects
3Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
709 homeson the public record across 9 projects
69,896 sq mbuilt-up filed
29,300 sq mland declared
₹192.14 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
NGAR PARISHAD DANAPUR NIZAMATMunicipal / Corporation1 of 2 projects
PATNA METROPOLITIAN AREA AUTHORITYMetropolitan / Development Authority1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Bihar · Registration filing
District
Patna
City / town
PATNA
Anchal (block)
Danapur
Mauja (revenue village)
Jamasauta
Village
MATHIAPUR (JAMSAUT)
Address
NEAR CAPITAL GREEN APPARTMENT, R.K. PURAM, DANAPUR KHAGAUL ROAD,PATNA
What’s nearby
SchoolsNo schools within 2km · Library 783m away
HealthcareHospital 925m away · Clinic within 2km
LifestylePark 1.2km away · Gym or sports centre 1.5km away
ShoppingSupermarket 1.3km away · Mall 676m away
Getting around
Expressway 1.1 kmPrimary road 2.3 kmRailway line 3.3 kmRailway station 3.7km away (Patliputra)Limited bus connectivity nearby
Water & environment
River 1.6 kmWater body 1.8 kmCanal 1.8 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹5.66 Cr declared to build 28 flats. What that works out to:

₹20.22 Lakhdeclared cost per flatall-in — land + construction
₹2,099/sq ftof built-up area₹22,591/sq m
17%of the cost is land₹873/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Bihar · Approved building plan
Building Permit

The promised possession date (31 Dec 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Bihar does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Bihar does not publish a complaints register. This read cannot speak to them either way.