HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
12
Parking
261 spaces
Land area
4,000 sq m
Sanctioned built-up
4,738 sq m
Recreational open space
400 sq m

Timeline

RERA registeredMar 2019
Proposed completionMar 2025
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Internal Roads & F…80%
Fire protection an…80%
Electrical meter r…80%
Sewerage (Chamber,…90%
Street Lighting90%
Water conservation…90%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Water Supply100%
Landscaping & Tree…100%
Aggregate area of …100%
Open Parking100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

GRAFFIC INFRASTRUCTURE PVT. LTD.

CompanyPromoter type
Aurangabad, MAHARASHTRABased in
2Projects
1City
2019–2026Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
2 projectson the public record across 2 projects
6,852 sq mbuilt-up filed
7,900 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Aurangabad Municipal CorporationMunicipal Corporation1 of 2 projects
Chhatrapati Sambhajingar Municipal CorporationMunicipal Corporationthis project1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Devlai
Taluka
Aurangabad
District
Aurangabad
Pincode
431001
Survey no.
GUT NO 86/PART AND 87/PART
North boundary
REMAINING LAND FOR GUT NO 87 PART
East boundary
LAND FOR GUT NO 134 AND 84
South boundary
REMAINING LAND FOR GUT NO 86 PART
West boundary
REMAINING LAND FOR GUT NO 86 AND 87 PART
What’s nearby
Schools3 schools within 1km · 4 educational institutions within 1km · College or university 249m away
HealthcareHospital 298m away · 7 clinics within 1km
LifestylePark 652m away · 9 restaurants and cafes within 1km
ShoppingSupermarket 1.4km away · Mall 1.1km away · Convenience store within 1km
Getting around
Expressway 194 m · Mondha Naka FlyoverPrimary road 1.1 km · Kranti ChowkRailway line 2.5 kmRailway station 3.4km away (Chhatrapati Sambhajinagar)Bus stop within 500m
04

Planning authority

MahaRERA · Approved building plan

Chhatrapati Sambhajingar Municipal Corporation

Municipal Corporation
Building Permit
Survey no. GUT NO 86/PART AND 87/PART

The promised possession date (30 Mar 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation

A city municipal corporation that sanctions projects within its own limits. It has approved 12,653 RERA projects across 34 districts about 1 in 2 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.