Complete project overview

MahaRERA · Registration filing
Floors
5
Buildings
2
Parking
12 spaces
Land area
1,100 sq m
Sanctioned built-up
1,183 sq m

Timeline

RERA registeredMay 2019
Proposed completionDec 2021
TodayJul 2026
Construction progress
Podiums0%
Landscaping & Tree…0%
Treatment And Disp…0%
Electrical meter r…0%
Open Parking0%
Water conservation…80%
Flat fit-out85%
OC-readiness85%
Water Supply90%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Stairs & lifts100%
External finishes100%
Sewerage (Chamber,…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

M/S - SWARAJYA GROUP

PartnershipPromoter type
Kolhapur, MAHARASHTRABased in
1Projects
1City
2019–2021Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kolki (CT)
Taluka
Phaltan
District
Satara
Pincode
415523
Survey no.
63/2
North boundary
9 M Wide Road
East boundary
9 M Wide Road
South boundary
Part S no 63-2-3
West boundary
Adj Plot No 38
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 801m away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 251 m · Dahiwadi Phaltan RoadPrimary road 984 mRailway line 4.1 kmRailway station 4.3km away (Phaltan)Limited bus connectivity nearby
Water & environment
Water body 772 mCanal 1.6 km · Right Bank Canal
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Town Planning Satara

Building Permit
Survey no. 63/2

The promised possession date (30 Dec 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Town Planning Satara

Planning authority

Has approved 14 RERA projects0.1% of Maharashtra.

an apartments market93% apartments · 7% plotted layouts. Apartments like yours are this body's core business.

Builders
14
On record
0 flats · 61 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.