HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
5
Buildings
2
Parking
1 spaces
Land area
566 sq m
Sanctioned built-up
962 sq m

Timeline

RERA registeredNov 2021
Proposed completionMar 2024
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

SHREE CONSTRUCTION COMPANY

PartnershipPromoter type
Nashik, MAHARASHTRABased in
2Projects
2Cities
2017–2024Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
2 projectson the public record across 2 projects
4,924 sq mbuilt-up filed
5,246 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Malegaon Municipal CorporationMunicipal Corporationthis project1 of 2 projects
Thane Municipal CorporationMunicipal Corporation1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Malegaon (M Corp.)
Taluka
Malegaon
District
Nashik
Pincode
423203
Survey no.
1175/2-1174
North boundary
S No 1173
East boundary
Existing Road
South boundary
1175-1
West boundary
S No 1163
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 472m away · 1 clinic within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 1.9 kmPrimary road 41 mNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 1.1 km · MosamWater body 1.4 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Malegaon Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 1175/2-1174

The promised possession date (31 Mar 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Malegaon Municipal Corporation

Municipal corporation

Has approved 8 RERA projects0% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
5
On record
330 flats · 0 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.