HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Plots
18 plots
Land area
37,120 sq m

Timeline

RERA registeredSep 2025
Proposed completionDec 2029
TodayJul 2026
Construction progress
Internal Roads & F…0%
Water Supply0%
Landscaping & Tree…0%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Terramarine Infrastructure LLP

Limited Liability PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kolgaon
Taluka
Alibag
District
Raigarh
Pincode
402201
Survey no.
Gat No. 92, 94/A/1, 95, 96, 97, 116, 118, 121/1, 121/2, 122, 137, 138
North boundary
Adj Gat No-134 and 135
East boundary
Adj Gat No-123, 94/A/2
South boundary
Adj Gat No-89, 99, 117
West boundary
Adj Gat No-114, 139, 140
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 1.2 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 321 mRiver 4.2 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Collector Of Raigad

Collector office
Layout Permit
Survey no. Gat No. 92, 94/A/1, 95, 96, 97, 116, 118, 121/1, 121/2, 122, 137, 138
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Collector Of Raigad

Planning authority

Has approved 16 RERA projects0.1% of Maharashtra.

an apartments market75% apartments · 25% plotted layouts. Layouts like yours are the smaller share here — this body mostly approves apartments.

Builders
16
On record
95 flats · 219 plots
Since
2017

More layout-heavy than Maharashtra overall — 25% plots here vs 5% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.