HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
5
Buildings
2
Parking
76 spaces
Land area
1,195 sq m
Sanctioned built-up
2,905 sq m

Timeline

RERA registeredJul 2024
Proposed completionDec 2025
TodayJul 2026
Construction progress
Podiums0%
Stilt floor0%
Water conservation…0%
Open Parking0%
Stairs & lifts90%
OC-readiness90%
Storm Water Drains90%
External finishes95%
Excavation100%
Basement (if any)100%
Plinth100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Water Supply100%
Sewerage (Chamber,…100%
Electrical meter r…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

PRAMOD PARSHARAM BUTALA

IndividualPromoter type
Ratnagiri, MAHARASHTRABased in
1Projects
1City
2024–2025Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Khed (M Cl)
Taluka
Khed
District
Ratnagiri
Pincode
415709
Survey no.
PLOT NO 28/1, KHED
North boundary
PLOT NO 23 24 25
East boundary
PLOT NO 28-2
South boundary
MUNICIPAL ROAD
West boundary
PLOT NO 26 27
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 242m away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 1.1 km · Mumbai Goa HighwayPrimary road 2 mRailway line 901 m · Konkan RailwayRailway station 1.4km away (Khed)Bus stop within 500m
Water & environment
Water body 652 mRiver 792 m · Jagbudi river
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Khed Municipal Council

Municipal Council
Building Permit
Survey no. PLOT NO 28/1, KHED

The promised possession date (31 Dec 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Khed Municipal Council

Municipal corporation

Has approved 8 RERA projects0% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
8
On record
30 flats · 0 plots
Since
2018

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.