Complete project overview
MahaRERA · Registration filing- Floors
- 37
- Parking
- 190 spaces
- Land area
- 866 sq m
- Sanctioned built-up
- 13,863 sq m
Timeline
RERA registeredSep 2019
Proposed completionDec 2029
TodayJul 2026
Construction progressPer-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
Stilt floor0%
Landscaping & Tree…0%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Internal Roads & F…100%
Water Supply100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Street Lighting100%
Treatment And Disp…100%
Solid Waste Manage…100%
Water conservation…100%
Energy managemcnt100%
Fire protection an…100%
Electrical meter r…100%
02
Builder’s track record
MahaRERA · Promoter registrationBramhacorp Limited
CompanyPromoter type
Pune, MAHARASHTRABased in
22Projects
2Cities
2017–presentActive
Timelineevery project, start → promised completion
Bramha Exuberance CF RESIDENCES T5 T6 and T7Bramha Vantage CF Residences T8Boulevard part of Towers Phase 1Bramhacorp Business Park T9-A1The Collection - Residential W1The Collection - Commercial W1The Collection - Residential W8Bramhacorp Business Park T9-A2Boulevard Tower A1BramhaCorp SmartThe Collection - W2 and W7The Collection PremiumBRAMHACORP TOWNHOUSE A1AUGUST TOWERS PH 1HUES OF SKYBOULEVARD TOWER A2THE COLLECTION - W5 AND W6BRAMHACORP TOWNHOUSE ABOULEVARD WING B 1SKY SUITES BY BRAMHACORP
Builder DNAthe whole portfolio, summed
1,120 homeson the public record across 22 projects
3,41,331 sq mbuilt-up filed
49,454 sq mland declared
These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.
Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
03
Location
MahaRERA · Registration filing- District
- Pune
- Pincode
- 411014
- Survey no.
- 7/1,7/2,7/3,7/4,7/5, 8/1/1/2, 38A/1B/1, 3/2
- North boundary
- By 5th Phase
- East boundary
- By F Residences-4th Phase
- South boundary
- By Proposed Development of buildings of 6th Phase
- West boundary
- By Proposed Development of buildings of 6th Phase
What’s nearby
SchoolsNearest school 1.6km away · Library 542m away
HealthcareHospital 1.1km away · 3 clinics within 1km
LifestylePark 2.0km away · Playground within 500m · Gym or sports centre 1.1km away
ShoppingSupermarket 91m away · Mall 1.4km away · Bank 696m away
Getting around
Expressway 1.2 km · Nagar RoadPrimary road 2.5 km · Mundhwa RoadRailway line 2.3 kmRailway station 1.1km away (Kalyani Nagar Station)Bus stop within 500mAirport 4.0km away
Water & environment
Water body 187 mCanal 891 m
distances only — not a flood assessmentLegal & regulatory recordFrom MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
LitigationNone declared to MahaRERA
None on record with MahaRERA against this project.
Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.