HORIZONMarkets
01

Complete project overview

RERA Punjab · Registration filing
Parking
442 spaces
Land area
7,999 sq m

Timeline

Project startedMar 2025
Proposed completionMar 2030
TodayJul 2026
02

Builder’s track record

RERA Punjab · Promoter registration

ALC Cybrum (Other than Individual)

PartnershipsPromoter type
1Projects
1Cities
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Punjab · Registration filing
District
Sahibzada Ajit Singh Nagar (Mohali)
Planning zone
Zone 1 - Master Plan Area of S.A.S. Nagar, New Chandigarh and Zirakpur.
Address
The Cybrum CP-04 Phase 8A, SAS Nagar Mohali , SAS Nagar Mohali Mohali , Sahibzada Ajit Singh Nagar (Mohali) , Punjab - 160062
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 853m away · Clinic within 2km · Doctor's clinic within 1km
LifestylePark 1.8km away
ShoppingSupermarket 1.5km away
Getting around
Expressway 2.9 km · Kharar-Banur RoadPrimary road 501 mRailway line 4.4 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 1.4 km
distances only — not a flood assessment
Declared external development
Roads0%
Electricity0%
Solid waste0%
Water supply0%
Sewage0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
Land, title & encumbrance
Land ownershipDeclared fully owned by the promoter
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Price analysisdeclared build cost — not a sale price

₹254.04 Cr declared. What that works out to:

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Punjab · Approved building plan
Building Permit
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Punjab does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Punjab does not publish a complaints register. This read cannot speak to them either way.