HORIZONMarkets
01

Complete project overview

RERA Punjab · Registration filing
Units
59 units
Unit mix
30 × 3 BHK · 29 × 4 BHK
Buildings
2
Parking
60 spaces
Land area
2,401 sq m

Timeline

Project startedJun 2021
Proposed completionJun 2026
TodayJul 2026

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

59 of 59 available
BuildingTypeArea sq mAvailable
TOWER 83 BHK9015 of 15
TOWER 84 BHK11315 of 15
TOWER 93 BHK9015 of 15
TOWER 94 BHK11314 of 14

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

RERA Punjab · Promoter registration

The Foothills Cooperative House Building Society Ltd (Other than Individual)

Co-operative SocietiesPromoter type
1Projects
1Cities
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Punjab · Registration filing
District
Sahibzada Ajit Singh Nagar (Mohali)
Planning zone
Zone 1 - Master Plan Area of S.A.S. Nagar, New Chandigarh and Zirakpur.
Address
GH Site No. 11, Sector-90-91, JLPL, Mohali , SAS Nagar Mohali , Sahibzada Ajit Singh Nagar (Mohali) , Punjab - 160071
What’s nearby
SchoolsNo schools within 2km · College or university 1.5km away
HealthcareHospital 439m away · Doctor's clinic within 1km
LifestylePark 1.5km away · Gym or sports centre 1.5km away
ShoppingSupermarket 1.7km away · Mall 1.8km away · ATM within 500m
Getting around
Expressway 1.0 kmPrimary road 127 m · SH12ARailway line 2.4 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 940 m
distances only — not a flood assessment
Declared external development
Water supply0%
Roads0%
Electricity0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
Land, title & encumbrance
Land ownershipDeclared fully owned by the promoter
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Price analysisdeclared build cost — not a sale price

₹34.39 Cr declared to build 59 flats. What that works out to:

₹58.29 Lakhdeclared cost per flatall-in — land + construction
₹5,346/sq ftof carpet area₹57,547/sq m

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Punjab · Approved building plan
Building Permit

The promised possession date (30 Jun 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Punjab does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Punjab does not publish a complaints register. This read cannot speak to them either way.