HORIZON
Share

TN/22/Building/0253/2025

TN/22/Building/0253/2025 · TNRERA · https://gethorizon.in/projects/tn-22-building-0253-2025-ep40l0zi

01

Complete project overview

TNRERA · Registration filing
Description
THE HEARTY Stilt cum Ground Floor + 1st Floor + 2nd Floor with 26 dwelling units comprised in Ward – B, Block-10, T.S.No.2/11A2 & 2/11C of Kodaikanal Village, Kodaikanal Taluk, Dindigul District.
Registration no.
TN/22/Building/0253/2025

Timeline

RERA registeredJul 2025
Proposed completionJul 2026
TodaySep 2026
02

Builder’s track record

TNRERA · Builder registration

ENERGY LIVINGSCAPES PRIVATE LIMITED & M C VENKATESH

ENERGY LIVINGSCAPES PRIVATE LIMITED & M C VENKATESHPromoter
1Projects
1Cities
2025–2026Active
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

TNRERA · Registration filing
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.6km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 1.5 km · Kodai Ghat RoadNo metro or railway within 5kmBus stop within 1km
Water & environment
River 229 m · Levinge StreamWater body 1.5 km
distances only — not a flood assessment
04

Government Guidance Rate

Tamil Nadu registration department

In Tamil Nadu it’s called the guideline value.

No government guidance rate is shown for this project.

Tamil Nadu publishes street-level guideline values; its full schedule isn't in Horizon's record yet.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

TNRERA · Approved building plan

Municipality

Municipality
Planning Permissionapproved 21 Jul 2025 · 1 yr ago

The promised possession date (31 Jul 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation

A city municipal corporation that approves within its own limits. It has approved 632 RERA projects about 1 in 6 in Tamil Nadu.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by TNRERA

07

Other projects nearby

The register · within 25 km

No other residential and mixed-use projects still under way are on the record within 25 km.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — TNRERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — TNRERA does not publish a complaints register. This read cannot speak to them either way.
  • Escrow — TNRERA does not publish escrow declarations. Whether buyer money is ring-fenced cannot be read here.