HORIZONMarkets
01

Complete project overview

TNRERA · Registration filing
Description
Construction of Stlit + 3 Floors with 09 Dwelling Units (Ground Floor + Three Floors) comprised in S.Nos.26/1B2 & 1A1B, 7th Street, Senthil Nagar Main Road (M to N182), Seevaram, Perungudi, Chennai District.
Registration no.
TN/29/Building/527/2022

Timeline

RERA registeredDec 2022
Proposed completionSep 2024
TodayJul 2026
02

Builder’s track record

TNRERA · Promoter registration

Raj Homes

Raj HomesPromoter
7Projects
2Cities
2019–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
131 homeson the public record across 7 projects
40,027 sq mbuilt-up filed
4,914 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Mira Bhayander Municipal CorporationMunicipal Corporation2 of 5 projects
City and Industrial Development Corporation (CIDCO)Development Authority1 of 5 projects
CMDA (Chennai Metropolitan Development Authority)CMDA (Chennai Metropolitan Development Authority)1 of 5 projects
Municipal CorporationMunicipal Corporationthis project1 of 5 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

TNRERA · Registration filing
04

Planning authority

TNRERA · Approved building plan

Municipal Corporation

Municipal Corporation
approved 27 Dec 2022 · 3 yrs ago
Planning Permission no. PPA/WDCN14/07954/2022

The promised possession date (30 Sep 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan PPA/WDCN14/07954/2022 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Municipal Corporation

A city municipal corporation that sanctions within its own limits. It has approved 632 RERA projects about 1 in 6 in Tamil Nadu.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — TNRERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — TNRERA does not publish a complaints register. This read cannot speak to them either way.
  • Escrow — TNRERA does not publish escrow declarations. Whether buyer money is ring-fenced cannot be read here.