TRIMURTI RESIDENCY

P52100049533 · MahaRERA · https://gethorizon.in/projects/trimurti-residency-chikhali-haveli-mxs0cqwv

01

Complete project overview

MahaRERA · Registration filing
Units
22 units
Floors
5
Buildings
2
Parking
33 spaces
Land area
465 sq m
Sanctioned built-up
1,116 sq m

Timeline

RERA registeredFeb 2023
Proposed completionFeb 2026
TodaySep 2026
Construction progress
Podiums0%
Flat fit-out0%
Water Supply0%
OC-readiness75%
Stairs & lifts80%
Internal finishes90%
External finishes95%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

TRIMURTI CONSTRUCTION AND DEVELOPERS

PartnershipPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2023–2026Active
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Chikhali
Taluka
Haveli
District
Pune
Pincode
411062
Survey no.
1648 P AT CHIKHALI
North boundary
PROPERTY OF MRS SUREKHA KUNDLIK KANGANE
East boundary
PROPERTY OF MR RAMCHANDRA PARANDE
South boundary
PROPERTY OF MR GAWARE AND MR MORE
West boundary
BY ROAD
What’s nearby
SchoolsNearest school 1.7km away
HealthcareHospital 626m away · 1 clinic within 1km
LifestyleNo parks within 2km
ShoppingSupermarket 823m away · ATM within 500m
Getting around
Expressway 2.9 kmPrimary road 1 m · Dehu - Alandi RoadNo metro or railway within 5kmBus stop within 1km
Water & environment
Water body 755 mRiver 843 m · Indrayani
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra IGR — Annual Statement of Rates

In Maharashtra it’s called the ready reckoner rate.

₹45,569per sq yd
₹54,500per sq m
Which rate
residential flat (built)
Matched to
The rate published for the village of “Chikhali”.
In force
2026-2027 schedule
Spread
₹39,724₹52,500 per sq yd across the places it was taken over

What this number is — and isn’t

  • The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
05

Planning authority

MahaRERA · Approved building plan

Pimpri Chinchwad Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 1648 P AT CHIKHALI

The promised possession date (4 Feb 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Pimpri Chinchwad Municipal Corporation

Municipal corporation

Has approved 1,391 RERA projectsabout 1 in 14 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,080
On record
9,009 flats · 249 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

2,915 residential projects still under way within 25 km. Step out ring by ring:

23 projects within 1 km — showing the nearest 6.

Pimpri ChinchawadResidential / Group Housing

SILVER CITY C AND D

SILVER GROUP

Oct 2020registered
Jun 2026target completion
Government Guidance Rate₹58,077/sq ydScale196 flatsAuthorityMahaRERA
ChikhaliOthers

Luxury Square

M/s. Sanco Spaces

Dec 2021registered
Dec 2026target completion
1 open complaintGovernment Guidance Rate₹45,569/sq ydScale179 flatsAuthorityMahaRERA
ChikhaliResidential / Group Housing

URBAN FRONT

ATMARAM MANOHAR GORE

Oct 2023registered
Dec 2026target completion
Government Guidance Rate₹45,569/sq ydScale46 flatsAuthorityMahaRERA
ChikhaliOthers

NAKODA HEIGHTS

SHREE NAKODA SPACES

Sep 2023registered
Dec 2026target completion
Government Guidance Rate₹45,569/sq ydScale49 flatsAuthorityMahaRERA
ChikhaliResidential / Group Housing

Mithila Harmony

Shree Bhagwati Infra

Jan 2024registered
Dec 2026target completion
Government Guidance Rate₹45,569/sq ydScale152 flatsAuthorityMahaRERA
Chikhali Bk.Residential / Group Housing

Tejas Apartment

SP Real Estate

Aug 2018registered
Dec 2031target completion
Scale24 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.