TVH Elanza

TNRERA/16/BLG/0368/2025 · TNRERA · https://gethorizon.in/projects/tvh-elanza-ej676lcl

01

Complete project overview

TNRERA · Registration filing
Description
Registration for Stilt + 5 Floors Residential Apartment Building with 35 dwelling units at comprised in T.S.No. 27, Block No: 12 of Puthur Village, Tiruchirappalli West Taluk, Tiruchirappalli District.
Registration no.
TNRERA/16/BLG/0368/2025

Timeline

RERA registeredOct 2025
Proposed completionMar 2026
TodaySep 2026
02

Builder’s track record

TNRERA · Builder registration

K N Mannivanan

K N MannivananPromoter
2Projects
1Cities
2025–2026Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
2 projectson the public record across 2 projects

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from K N Mannivanan— the full portfolio →

03

Location

TNRERA · Registration filing
What’s nearby
Schools1 school within 500m · College or university 1.8km away
HealthcareHospital 92m away · 17 clinics within 1km · Pharmacy within 500m
LifestylePark 810m away · Gym or sports centre 1.2km away · 3 restaurants and cafes within 1km
ShoppingSupermarket 804m away · Mall 103m away · Bank 145m away
Getting around
Expressway 2.2 km · Aristo Roundabout FlyoverPrimary road 575 m · Students roadRailway line 1.4 kmRailway station 1.7km away (Tiruchchirapalli Fort)2 bus stops within 500m
Water & environment
Water body 601 mCanal 879 m · Uyyakondan Canal
distances only — not a flood assessment
04

Government Guidance Rate

Tamil Nadu registration department

In Tamil Nadu it’s called the guideline value.

No government guidance rate is shown for this project.

Tamil Nadu publishes street-level guideline values; its full schedule isn't in Horizon's record yet.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

TNRERA · Approved building plan

Town & Country Planning (DTCP)

Town & Country Planning (DTCP)
approved 31 Oct 2025 · 11 mo ago
Planning Permission no. 66/2024

The promised possession date (31 Mar 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

Verify it yourself — look up plan 66/2024 on the approving authority’s portal to confirm the approval.

The approving body, at scale

Town & Country Planning (DTCP)

Town & country planning

Has approved 756 RERA projectsabout 1 in 5 in Tamil Nadu.

Builders
467
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by TNRERA

07

Other projects nearby

The register · within 25 km

26 residential and mixed-use projects still under way within 25 km. Step out ring by ring:

Of the 18 projects the radar draws within 6 km — every kind, every stage — 14 are residential and mixed-use projects still under way. This list keeps only those, and looks further out.

1 project within 1 km — showing the nearest 1.

280 m away

ARENYA TOWERS

V.Kailasam Proprietor of M/s. Rangga Builders

Feb 2025registered
Feb 2028target completion
AuthorityTNRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — TNRERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — TNRERA does not publish a complaints register. This read cannot speak to them either way.
  • Escrow — TNRERA does not publish escrow declarations. Whether buyer money is ring-fenced cannot be read here.