Complete project overview

MahaRERA · Registration filing
Floors
11
Buildings
2
Parking
59 spaces
Land area
11,583 sq m
Sanctioned built-up
10,644 sq m
Recreational open space
859 sq m

Timeline

RERA registeredFeb 2018
Proposed completionDec 2022
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Water Supply0%
Landscaping & Tree…0%
Solid Waste Manage…0%
Aggregate area of …0%
Open Parking0%
Fire protection an…30%
OC-readiness50%
Internal Roads & F…50%
Sewerage (Chamber,…50%
Storm Water Drains50%
Energy managemcnt50%
Electrical meter r…75%
Stairs & lifts95%
Internal finishes97%
Flat fit-out97%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
External finishes100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

TWIN DEVELOPERS

PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2018–2022Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kurla
Taluka
Kurla
District
Mumbai Suburban
Pincode
400070
Survey no.
198/1
North boundary
CST ROAD
East boundary
LAND BELONGING TO KISHANCHAND REWACHAND
South boundary
CTS NO 1 PART SUBDIVISION NO 1 B-1
West boundary
CTS NO 1
What’s nearby
Schools1 school within 1km
HealthcareHospital 341m away · 1 clinic within 1km · Pharmacy within 1km
LifestylePark 780m away · 12+ restaurants and cafes within 1km
ShoppingSupermarket 768m away · Bank 344m away · ATM within 500m
Getting around
Expressway 39 mPrimary road 217 m · BKC - SCLR ConnectorRailway line 1.2 km · Central Railway (Slow)Railway station 1.3km away (Kurla)7 bus stops within 500m
Water & environment
River 155 m · Mithi River
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Slum

Building Permit
Survey no. 198/1

The promised possession date (30 Dec 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation11 cases on record, earliest 2007
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 1 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.