HORIZON
Share

Uday Heights

P52100077400 · MahaRERA · https://gethorizon.in/projects/uday-heights-kharadi-pune-eu7wmgcg

Registration lapsed

This project’s MahaRERA registration has lapsed— it expired and was not renewed. A lapsed project may be stalled, finished-but-not-updated, or abandoned; the record stops here and RERA’s ongoing protections may no longer apply. Confirm the current status directly with MahaRERA before you rely on anything below.

01

Complete project overview

MahaRERA · Registration filing
Units
80 units
Floors
12
Buildings
2
Parking
94 spaces
Land area
2,022 sq m
Sanctioned built-up
5,258 sq m

Timeline

RERA registeredAug 2024
Proposed completionJan 2026
TodaySep 2026
02

Builder’s track record

MahaRERA · Builder registration

SAIGURU DEVELOPERS (AOP)

CompanyPromoter type
Pune, MAHARASHTRABased in
1Projects
1Cities
2024–2026Active
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
District
Pune
Pincode
411014
Survey no.
Survey No. 4/1 Part
North boundary
Tanishq Society
East boundary
Wardhaman square society
South boundary
Road
West boundary
Vandan Building
What’s nearby
Schools1 school within 500m · College or university 1.9km away · Library 421m away
HealthcareHospital 308m away · 2 clinics within 1km · Pharmacy within 500m
LifestylePark 947m away · 26+ restaurants and cafes within 1km
ShoppingSupermarket 508m away · Mall 729m away · Convenience store within 500m
Getting around
Expressway 712 m · Kharadi BypassPrimary road 2.2 km · Mundhwa RoadRailway line 3.0 km · Pune - Daund Railway LineRailway station 3.2km away (Hadapsar Railway Station)Limited bus connectivity nearbyAirport 4.5km away
Water & environment
River 705 m · Mula-Mutha
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Maharashtra's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Kharadhi

Building Permit
Survey no. Survey No. 4/1 Part

The promised possession date (31 Jan 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that approved this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

07

Other projects nearby

The register · within 25 km

3,016 residential projects still under way within 25 km. Step out ring by ring:

13 projects within 1 km — showing the nearest 6.

KHARADIOthers

Palladio Kharadi Central

Vilas Javdekar Eco Homes

Apr 2023registered
Jun 2027target completion
Scale350 flatsAuthorityMahaRERA
KharadiResidential / Group Housing

SHUBH SHAGUN

Shubh Housing

Nov 2018registered
Dec 2026target completion
Scale327 flatsAuthorityMahaRERA
KHARADIResidential / Group Housing

MAJESTIQUE MARBELLA PHASE 1

Majestique Empire LLP

Jul 2020registered
Jun 2026target completion
Scale177 flatsAuthorityMahaRERA
KHARADIResidential / Group Housing

MAJESTIQUE MARBELLA PHASE V

Majestique Empire LLP

Jan 2022registered
Dec 2026target completion
Scale157 flatsAuthorityMahaRERA
KharadiOthers

Palladio Kharadi Central Phase 2

Vilas Javdekar Eco Homes

Oct 2024registered
Dec 2028target completion
1 open complaintScale377 flatsAuthorityMahaRERA
PuneOthers

Raichandani Aura

Raichandani Constructions Private Limited

Jan 2025registered
Aug 2028target completion
Scale90 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.