Complete project overview

MahaRERA · Registration filing
Floors
17
Buildings
8
Parking
378 spaces
Land area
11,205 sq m
Sanctioned built-up
19,066 sq m
Recreational open space
3,232 sq m

Timeline

RERA registeredJul 2017
Proposed completionDec 2021
TodayJul 2026
Construction progress
Podiums0%
Energy managemcnt0%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Internal Roads & F…100%
Water Supply100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Landscaping & Tree…100%
Street Lighting100%
Community Building…100%
Treatment And Disp…100%
Solid Waste Manage…100%
Water conservation…100%
Fire protection an…100%
Electrical meter r…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Kakade Vtp Associates

PartnershipPromoter type
Pune, MAHARASHTRABased in
2Projects
1City
2017–2021Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
41 plotson the public record across 2 projects
19,066 sq mbuilt-up filed
4,301 sq mplotted area
15,506 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Talegaon Dabhade (R)
Taluka
Mawal
District
Pune
Pincode
410506
Survey no.
s no 23 part gat no 81 part
North boundary
part of gat no 81 part sno 23
East boundary
part of gat no 81 sno23
South boundary
part gat no 81 part sno 23
West boundary
part of gat no 81 part sno 23
What’s nearby
Schools1 school within 500m · 6 educational institutions within 1km · College or university 410m away
HealthcareHospital 288m away · Clinic within 2km
LifestylePark 800m away · Gym or sports centre 902m away · 4 restaurants and cafes within 1km
ShoppingSupermarket 563m away · Mall 1.3km away
Getting around
Expressway 260 m · Urse Talegaon RoadPrimary road 4.1 km · Urse Talegaon RoadRailway line 678 m · Mumbai–Pune RailwayRailway station 908m away (Talegaon)Limited bus connectivity nearby
Water & environment
Water body 1.5 kmRiver 1.7 km · Indrayani
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pune Metropolitan Region Development Authority

Metropolitan Development Authority
Building Permit
Survey no. s no 23 part gat no 81 part

The promised possession date (31 Dec 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pune Metropolitan Region Development Authority

Metropolitan / development authority

Has approved 1,013 RERA projectsabout 1 in 20 in Maharashtra.

an apartments market87% apartments · 13% plotted layouts. Apartments like yours are this body's core business.

Builders
604
On record
21,940 flats · 10,299 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
Compliance4 non-compliance notices on record
Appeals1 appeal before the tribunal
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

15 complaints on MahaRERA’s register for this project 12 disposed, 3 still open.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.