Complete project overview

RERA Telangana · Registration filing
Units
67 units
Unit mix
63 × 4BHK, 4 × Amenities
Saleable area
478–1559 sq mper unit, as filed
Floors
4
Buildings
11
Land area
24,026 sq m
Built-up area
22,194 sq m

Timeline

RERA approvedOct 2024
Proposed completionOct 2027
TodayJul 2026
Construction progress

8.5% overall, as filed

Basement & plinth0%
Podiums0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Excavation85%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

67 of 67 available
BuildingFloorTypeArea sq mAvailable
AMENITIES1Amenities5451 of 1
AMENITIES2Amenities7681 of 1
AMENITIES3Amenities5821 of 1
AMENITIES4Amenities6961 of 1
BLOCK A14BHKmortgaged5671 of 1
BLOCK A14BHKmortgaged5191 of 1
BLOCK A14BHKmortgaged4783 of 3
BLOCK A14BHKmortgaged7111 of 1
BLOCK B14BHK4783 of 3
BLOCK B14BHK7111 of 1
BLOCK B14BHKmortgaged7111 of 1
BLOCK B14BHKmortgaged4783 of 3
BLOCK B14BHKmortgaged5191 of 1
BLOCK B14BHKmortgaged5671 of 1
BLOCK B14BHK5671 of 1
BLOCK B14BHK5191 of 1
BLOCK C14BHK5674 of 4
BLOCK C14BHK5196 of 6
BLOCK C14BHK4782 of 2
BLOCK D14BHK6421 of 1
BLOCK D14BHK4787 of 7
BLOCK D14BHK5672 of 2
BLOCK E14BHK6421 of 1
BLOCK E14BHK4781 of 1
BLOCK E14BHK5194 of 4
BLOCK E14BHK5672 of 2
BLOCK F14BHK1,5591 of 1
BLOCK G14BHK7112 of 2
BLOCK H14BHK7112 of 2
BLOCK H14BHK5671 of 1
BLOCK I14BHK5672 of 2
BLOCK I14BHK7111 of 1
BLOCK I14BHK5192 of 2
BLOCK J14BHK4784 of 4

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

ADITI HOMES INDIA PRIVATE LIMITED

CompanyPromoter type
Hyderabad, TelanganaBased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
TELLAPUR
Mandal
RC PURAM
District
Sangareddy
Pincode
502032
North boundary
OTHERS LAND
East boundary
ROAD
South boundary
OTHERS LAND
West boundary
OTHERS LAND
What’s nearby
SchoolsNearest school 1.2km away · College or university 1.9km away · Kindergarten within 500m
HealthcareNearest hospital 2.7km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 4.8 kmPrimary road 3.2 km · Nallagandla FlyoverRailway line 1.2 kmRailway station 1.3km away (Telapur)Limited bus connectivity nearby
Water & environment
Water body 377 m
distances only — not a flood assessment
Declared external development
Roads15%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit
Survey no. SY NOS 83,83/A,85,85/A/1,85/P,86,86/A/2,86/AA/2,88,88/P,88/AA/2,88/AA/3,88/A/1,95/AA/2 AND 95/A/1
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.