HORIZONMarkets
01

Complete project overview

RERA Bihar · Registration filing
Units
358 units
Unit mix
162 × 3 BHK · 76 × 1 BHK · 37 × 2 BHK · 34 × 3.5 BHK · 19 × 4 BHK · 18 × 2.5 BHK
Buildings
20
Parking
307 spaces
Land area
9,595 sq m
Built-up area
58,751 sq m

Timeline

RERA registeredAug 2020
Project startedJan 2021
Proposed completionDec 2024
TodayJul 2026

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

358 units across 31 batches
BuildingTypeArea sq mCount
Venus EmpirePenthouse01
Venus Empire (Unit-1)3 BHK5419
Venus Empire (Unit-10)3 BHK5318
Venus Empire (Unit-10)Penthouse01
Venus Empire (Unit-11)2.5 BHK4618
Venus Empire (Unit-11)Penthouse01
Venus Empire (Unit-12)3 BHK4618
Venus Empire (Unit-12)Penthouse01
Venus Empire (Unit-13)2 BHK3318
Venus Empire (Unit-13)Penthouse01
Venus Empire (Unit-14 EWS)2 BHK2819
Venus Empire (Unit-15)3 BHK4419
Venus Empire (Unit-16 EWS)1 BHK1619
Venus Empire (Unit-17 EWS)1 BHK1619
Venus Empire (Unit-18 EWS)1 BHK1619
Venus Empire (Unit-19 EWS)1 BHK1619
Venus Empire (Unit-2)3 BHK5718
Venus Empire (Unit-2)Penthouse01
Venus Empire (Unit-3)4 BHK8319
Venus Empire (Unit-4)3.5 BHK7217
Venus Empire (Unit-4)Penthouse01
Venus Empire (Unit-5)3.5 BHK7217
Venus Empire (Unit-5)Penthouse01
Venus Empire (Unit-6)3 BHK6117
Venus Empire (Unit-6)Penthouse01
Venus Empire (Unit-7)3 BHK6117
Venus Empire (Unit-7)Penthouse01
Venus Empire (Unit-8)3 BHK5118
Venus Empire (Unit-8)Penthouse01
Venus Empire (Unit-9)3 BHK5118
Venus Empire (Unit-9)Penthouse01

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RERA Bihar · Promoter registration

VENUS STAR CONSTRUCTION PVT. LTD.

CompanyPromoter type
Patna, BiharBased in
---Select---Also RERA-registered in
3Projects
3Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
2,186 homeson the public record across 3 projects
3,90,169 sq mbuilt-up filed
73,611 sq mland declared
₹198.91 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Bihar · Registration filing
District
Patna
City / town
Danapur, Patna
Anchal (block)
Danapur
Mauja (revenue village)
Adampur Khurda
Village
Mauza- Adampur, Vijay Singh Yadav Path, Danapur, Patna
Address
Venus Empire, Mauza- Adampur, Vijay Singh Yadav Path, Near Holy Mission School, Danapur, Patna.
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.4km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 2.8 kmPrimary road 1.7 km · Neora RoadRailway line 1.7 kmRailway station 2.1km away (Danapur)Limited bus connectivity nearby
Water & environment
Water body 1.1 km · chhat puja talabCanal 2.6 km · Barun Canal
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹103.61 Cr declared to build 358 flats. What that works out to:

₹28.94 Lakhdeclared cost per flatall-in — land + construction
₹1,638/sq ftof built-up area₹17,636/sq m
12%of the cost is land₹1,157/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Bihar · Approved building plan
Building Permit

The promised possession date (31 Dec 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Bihar does not publish quarterly progress reports. How far along it actually is cannot be read here.