HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Plots
22 plots
Land area
4,571 sq m
Sanctioned built-up
7,090 sq m
Recreational open space
722 sq m

Timeline

RERA registeredJul 2023
Proposed completionMar 2024
TodayJul 2026
Construction progress
Electrical meter r…15%
Water Supply36%
Landscaping & Tree…87%
Street Lighting87%
Internal Roads & F…90%
Storm Water Drains94%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Pramod Wamanrao Kolhe

IndividualPromoter type
Nagpur, MAHARASHTRABased in
1Projects
1City
2023–2024Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kelzar
Taluka
Seloo
District
Wardha
Pincode
442104
Survey no.
599/1
North boundary
Agricultural land
East boundary
National Highway Road
South boundary
Agricultural land
West boundary
Agricultural land of Rahul Patil
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 3.6 km · Nagpur Tuljapur RoadPrimary road 4.9 kmRailway line 1.8 kmRailway station 1.9km away (Seloo Road)Limited bus connectivity nearby
Water & environment
River 672 m · Bor RiverWater body 4.5 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Town Planning

Layout Permit
Survey no. 599/1

The promised possession date (31 Mar 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Town Planning

Planning authority

Has approved 21 RERA projects0.1% of Maharashtra.

an apartments market71% apartments · 29% plotted layouts. Layouts like yours are the smaller share here — this body mostly approves apartments.

Builders
16
On record
466 flats · 542 plots
Reach
8 districts
Since
2017

More layout-heavy than Maharashtra overall — 29% plots here vs 5% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.