Complete project overview

MahaRERA · Registration filing
Buildings
2
Land area
2,393 sq m

Timeline

RERA registeredMar 2026
Proposed completionMar 2032
TodayJul 2026
Construction progress
Excavation0%
Basement (if any)0%
Podiums0%
Plinth0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Nensee Constructions Private Limited

CompanyPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2026–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Chembur
Taluka
CTSO Chembur
District
Mumbai Suburban
Pincode
400071
Survey no.
1721, 1721/1 to 33
North boundary
By Property bearing CTS No.1720 and beyond that by Railway Track
East boundary
Partly by Golf Club and Beyond that public road
South boundary
Partly by Govt. and partly by land of Dharmashalla and partly by property bearing CTS No.1723
West boundary
Partly by mahul chembur road, now known as ramkrishna chemburkar marg, and partly by the land of dharmashala
What’s nearby
SchoolsNearest school 1.1km away
HealthcareHospital 198m away · 4 clinics within 1km
Lifestyle1 park within 500m · Gym or sports centre 185m away · 23+ restaurants and cafes within 1km
ShoppingSupermarket 868m away · Mall 1.8km away · Bank 407m away
Getting around
Expressway 386 mPrimary road 1.4 km · Sewri-Chembur RoadRailway line 813 mRailway station 266m away (VNP & RC Marg Junction)4 bus stops within 500m
Water & environment
Water body 156 m · Teen Talav
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation · MCGM
Building Permit
Survey no. 1721, 1721/1 to 33
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation3 cases on record, earliest 2012
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.