Complete project overview

MahaRERA · Registration filing
Floors
9
Buildings
2
Parking
26 spaces
Land area
463 sq m
Sanctioned built-up
1,529 sq m

Timeline

RERA registeredJun 2025
Proposed completionSep 2027
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Stairs & lifts0%
OC-readiness0%
Fire protection an…0%
Electrical meter r…0%
External finishes30%
Flat fit-out40%
Internal finishes50%
Superstructure90%
Excavation100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

VARAD RAJA REALTY

PartnershipPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Thane (M Corp.)
Taluka
Thane
District
Thane
Pincode
400602
Survey no.
CTS NO 51 TIKA NO 15, CTS NO 47 TIKA NO 15 SECTOR NO. 2 MOUJE THANE
North boundary
VASANT VILLA
East boundary
RBI COLONY
South boundary
MUNICIPAL ROAD
West boundary
MUNICIPAL ROAD AND RADHE SHAM SOCIETY
What’s nearby
SchoolsNearest school 1.7km away · 4 educational institutions within 1km · College or university 953m away
HealthcareHospital 91m away · 14 clinics within 1km · Pharmacy within 500m
Lifestyle2 parks within 500m · Gym or sports centre 833m away · 34+ restaurants and cafes within 1km
ShoppingSupermarket 158m away · Convenience store within 1km · Bank 180m away
Getting around
Expressway 751 mPrimary road 365 m · Lal Bahadur Shastri MargRailway line 454 mRailway station 592m away (Thane)16 bus stops within 500m
Water & environment
Water body 805 m · Hariyali Talao
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Thane Municipal Corporation

Municipal Corporation
Building Permit
Survey no. CTS NO 51 TIKA NO 15, CTS NO 47 TIKA NO 15 SECTOR NO. 2 MOUJE THANE
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Thane Municipal Corporation

Municipal corporation

Has approved 489 RERA projects2.4% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
318
On record
7,890 flats · 0 plots
Reach
5 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.