HORIZONMarkets
Registration lapsed

This project’s MahaRERA registration has lapsed— it expired and was not renewed. A lapsed project may be stalled, finished-but-not-updated, or abandoned; the record stops here and RERA’s ongoing protections may no longer apply. Confirm the current status directly with MahaRERA before you rely on anything below.

01

Complete project overview

MahaRERA · Registration filing
Floors
9
Buildings
2
Parking
30 spaces
Land area
1,297 sq m
Sanctioned built-up
990 sq m

Timeline

RERA registeredDec 2018
Proposed completionDec 2023
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

Shailesh Pandurang Pednekar

IndividualPromoter type
Ratnagiri, MAHARASHTRABased in
1Projects
1City
2018–2023Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Nachane (CT)
Taluka
Ratnagiri
District
Ratnagiri
Pincode
415639
Survey no.
S No 188 H No B1 CTS No 85/1A/12A/1 Plot no 1
North boundary
ROAD
East boundary
CTS No 85 1A 14
South boundary
ROAD
West boundary
CTS No 85 1A 12A 2
What’s nearby
SchoolsNearest school 1.8km away · College or university 2.0km away
HealthcareHospital 814m away · 2 clinics within 1km · Pharmacy within 1km
LifestyleNo parks within 2km · Gym or sports centre 1.1km away · Swimming pool within 2km
ShoppingSupermarket 1.2km away · Bank 855m away
Getting around
Expressway 1.3 km · Hodekar RoadPrimary road 592 mRailway line 3.2 kmRailway station 4.9km away (Ratnagiri)Limited bus connectivity nearby
Water & environment
River 1.6 km · Kajvi
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Ratnagiri Nagar Parishad Ratnagiri

Municipal Council
Building Permit
Survey no. S No 188 H No B1 CTS No 85/1A/12A/1 Plot no 1

The promised possession date (30 Dec 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Ratnagiri Nagar Parishad Ratnagiri

Municipal corporation

Has approved 8 RERA projects0% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
8
On record
0 flats · 0 plots
Since
2018

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.