Complete project overview

MahaRERA · Registration filing
Floors
7
Buildings
2
Parking
62 spaces
Land area
3,374 sq m
Sanctioned built-up
3,055 sq m
Recreational open space
1 sq m

Timeline

RERA registeredJul 2023
Proposed completionJun 2025
TodayJul 2026
Construction progress
Water Supply0%
Sewerage (Chamber,…0%
Water conservation…0%
Electrical meter r…0%
Open Parking0%
OC-readiness70%
Internal finishes95%
Flat fit-out95%
Stairs & lifts95%
External finishes95%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

VISHWACON ENGINEERS

PartnershipPromoter type
Satara, MAHARASHTRABased in
1Projects
1City
2023–2025Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Karanje Tarf Satara (CT)
Taluka
Satara
District
Satara
Pincode
415001
Survey no.
PLOT NO. 7 SURVEY NO. 194/2B/2,
North boundary
PLOT NO 6
East boundary
PLOT NO 1 TO 5 ROAD OPEN SPACE AND AMENITIES SPACE
South boundary
S NO 172
West boundary
S NO 194 2A
What’s nearby
Schools1 school within 1km · College or university 1.3km away
HealthcareHospital 482m away · 5 clinics within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 1.6 kmPrimary road 224 mNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Canal 300 mWater body 1.5 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Others

Building Permit
Survey no. PLOT NO. 7 SURVEY NO. 194/2B/2,

The promised possession date (30 Jun 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Others

Planning authority

Has approved 30 RERA projects0.1% of Maharashtra.

an apartments market97% apartments · 3% plotted layouts. Apartments like yours are this body's core business.

Builders
27
On record
813 flats · 264 plots
Reach
11 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation2 cases on record, earliest 2023
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 1 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.