HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
2
Parking
31 spaces
Land area
580 sq m
Sanctioned built-up
1,526 sq m

Timeline

RERA registeredNov 2025
Proposed completionJun 2028
TodayJul 2026
Construction progress
Excavation0%
Plinth0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Landscaping & Tree…0%
Water conservation…0%
Electrical meter r…0%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

M/s Sunrise Infra

PartnershipPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Baramati (M Cl)
Taluka
Baramati
District
Pune
Pincode
413102
Survey no.
Gut No. 149/2, Plot No. 3 & 4, of Mouje - Jalochi, Baramati, Pune 413102
North boundary
12 Mtrs. Wide Road
East boundary
Plot no 05
South boundary
Gat No 150
West boundary
Gat No 150
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 285m away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 3.0 km · Baramati BypassPrimary road 266 m · Baramati Bhigwan RoadRailway line 1.1 kmRailway station 2.4km away (Baramati)Limited bus connectivity nearby
Water & environment
Canal 1.1 kmRiver 3.4 km · Karha River
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Baramati Municipal Council

Municipal Council
Building Permit
Survey no. Gut No. 149/2, Plot No. 3 & 4, of Mouje - Jalochi, Baramati, Pune 413102
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Baramati Municipal Council

Municipal corporation

Has approved 97 RERA projects0.5% of Maharashtra.

an apartments market98% apartments · 2% plotted layouts. Apartments like yours are this body's core business.

Builders
80
On record
656 flats · 211 plots
Since
2019

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.