HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
17
Buildings
2
Parking
24 spaces
Land area
3,259 sq m
Sanctioned built-up
4,037 sq m

Timeline

RERA registeredSep 2019
Proposed completionDec 2023
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

WESTERNCITY TOWNSHIPS LLP

PartnershipPromoter type
Pune, MAHARASHTRABased in
2Projects
1City
2017–2023Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
137 homeson the public record across 2 projects
14,234 sq mbuilt-up filed
7,233 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Pashan
Taluka
Haveli
District
Pune
Pincode
411045
Survey no.
135/5/1,135/5/2,135/6,135/6/1
North boundary
SNO135PART
East boundary
BUILDINGC
South boundary
SNO135PART
West boundary
CTS NO2146
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 4.8km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 554 m · Newasa Shevgaon RoadNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 697 mRiver 2.2 km · Dhora
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Poona Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 135/5/1,135/5/2,135/6,135/6/1

The promised possession date (30 Dec 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Poona Municipal Corporation

Municipal corporation

Has approved 61 RERA projects0.3% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
54
On record
631 flats · 0 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

3 complaints on MahaRERA’s register for this project 1 disposed, 2 still open.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.