HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
33
Buildings
2
Parking
1 spaces
Land area
4,222 sq m
Sanctioned built-up
15,361 sq m

Timeline

RERA registeredMay 2024
Proposed completionDec 2028
TodayJul 2026
Construction progress
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Stilt floor60%
Superstructure62%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

PRAMANIK HOMES LLP

PartnershipPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Mira-Bhayandar (M Corp.)
Taluka
Thane
District
Thane
Pincode
401107
Survey no.
OLD SURVEY NO 272 NEW SURVEY NO 84 HISSA NUMBER 3P, 4
North boundary
30 MTR WIDE ROAD
East boundary
OLD SURVEY NO 273 HISSA NO 4
South boundary
OLD SURVEY NO 272 NEW SURVEY NO 84 HISSA NUMBER 5
West boundary
15 MTR DP ROAD
What’s nearby
Schools1 school within 1km
HealthcareHospital 500m away · 1 clinic within 1km
LifestyleNo parks within 2km · Gym or sports centre 565m away · 3 restaurants and cafes within 1km
ShoppingSupermarket 1.7km away · Mall 1.4km away
Getting around
Expressway 1.9 km · Western Express HighwayPrimary road 1.8 km · Mira Bhayandar RoadRailway line 2.7 kmMetro station 2.3km away (Kashigaon)Bus stop within 1km
Water & environment
Water body 143 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Mira Bhayandar Municipal Corporation

Municipal Corporation
Building Permit
Survey no. OLD SURVEY NO 272 NEW SURVEY NO 84 HISSA NUMBER 3P, 4
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Mira Bhayandar Municipal Corporation

Municipal corporation

Has approved 127 RERA projects0.6% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
101
On record
2,811 flats · 0 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.