Complete project overview

K-RERA · Registration filing
Units
8 units
Mix
6 × 3BHK · 2 × 2BHK
Buildings
1
Land area
625 sq m
Floor area
1,582 sq m
Description
Waterlilly Apartments

Timeline

Project startedNov 2011
RERA registeredFeb 2026
Proposed completionApr 2026
TodayJul 2026
Construction progress

88% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

8 of 8 available
TypeArea sq mAvailable
3BHK1132 of 2
3BHK1132 of 2
3BHK1132 of 2
2BHK1122 of 2

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

Kizhakkekara Benchmark Builders

PartnershipPromoter type
Ernakulam, KeralaBased in
No — the promoter declared this is a first projectDeclared prior experience
1Projects
1Cities
2026–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
Konthuruthy
Village
ELAMKULAM
Taluk
Kanayannur
District
Ernakulam
Pincode
682013
Survey no.
Sy 966
Patta no.
25545
What’s nearby
SchoolsNearest school 1.5km away · 5 educational institutions within 1km · College or university 1.8km away
HealthcareHospital 308m away · 13 clinics within 1km · Pharmacy within 500m
Lifestyle1 park within 500m · Gym or sports centre 116m away · 70+ restaurants and cafes within 1km
ShoppingSupermarket 44m away · Mall 1.7km away · Convenience store within 500m
Getting around
Expressway 1.8 kmPrimary road 467 m · Sahodaran Ayyappan RoadRailway line 926 mMetro station 661m away (Kadavanthra)5 bus stops within 500mAirport 4.2km away
Water & environment
Water body 238 m · Temple Pond
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Kochi Municipal Corporation

Municipal Corporation
approved 23 Nov 2011 · 14 yrs ago
Building Permit no. MOP2.COC/113/11Survey no. Sy 966

The promised possession date (5 Apr 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan MOP2.COC/113/11 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Kochi Municipal Corporation

Municipal corporation / municipality

Has approved 92 RERA projectsabout 1 in 17 in Kerala.

an apartments market97% apartments · 3% plotted layouts. Apartments like yours are this body's core business.

Builders
50
On record
4,090 flats · 12 plots
Since
2021

More apartment-heavy than Kerala overall — 97% apartments here vs 81% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.